CalcWorldHub
Free online calculator · no signup

Excavation spoil truck loads and fleet duration calculator

Estimate the number of truck loads and working shifts to haul excavated spoil using swell, truck capacity, cycle time, and fleet size.

4,000 tools
Excavation spoil truck loads and fleet duration calculator — In-place excavation volume (m³), Loose-volume swell (%), Truck loose-volume capacity (m³) and calculation method
Excavation spoil truck loads and fleet duration calculator: inputs and calculation method.

How to use this calculator

Estimate the number of truck loads and working shifts to haul excavated spoil using swell, truck capacity, cycle time, and fleet size.

  1. Enter In-place excavation volume (m³), Loose-volume swell (%), Truck loose-volume capacity (m³), Average truck cycle (minutes), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Excavation spoil truck loads and fleet duration explained

Loose spoil volume225m³
Loose spoil volume: 225 m³ in the worked scenario.

How the calculation works

Loose volume = in-place volume × (1 + swell/100); loads = ceil(loose volume / truck capacity); shifts = ceil(loads / (fleet × trips per truck per shift)).

The estimate first expands the excavated volume by the entered swell allowance, rounds up to whole truck loads, then estimates loads completed per shift from cycle time and productive shift minutes.

Set up the calculation

volume — In-place excavation volume (m³)
Measured or calculated volume before excavation loosens the soil.
swell — Loose-volume swell (%)
Increase from in-place volume to the hauled loose volume; use a project-specific estimate.
capacity — Truck loose-volume capacity (m³)
Usable volume per truck trip, subject to any lower legal payload limit.
cycle — Average truck cycle (minutes)
Load, travel, tip, and return time for one truck.
fleet — Available trucks
Trucks assigned to this haul operation. Enter a whole number.
shift — Productive shift time (hours)
Scheduled haul time available per shift.
util — Time utilization (%)
Share of shift available after ordinary interruptions and idle time.

Limits of this model

Swell, volume capacity, and cycle time are user estimates. The model assumes similar repeat cycles and no queues; check truck payload, road access, disposal rules, and site conditions separately.

Check this example

In-place excavation volume (m³) = 180; Loose-volume swell (%) = 25; Truck loose-volume capacity (m³) = 8; Average truck cycle (minutes) = 42; Available trucks = 3; Productive shift time (hours) = 8; Time utilization (%) = 80.

  • Loose spoil volume: 225 m³
  • Truck trips required: 29 loads
  • Trips per truck per shift: 9 trips
  • Estimated hauling shifts: 2 shifts
  • Total truck cycle time: 20.3 truck-hours

Excavating 180 m³ with 25% swell creates 225 m³ loose. At 8 m³ per trip that is 29 loads; three trucks making nine trips each per shift require two shifts.

Reading the outputs

The main result is excavation spoil haul trips and shifts; supporting outputs are labeled with their own units.

Frequently asked questions

What does excavation spoil truck loads and fleet duration show?

Excavating 180 m³ with 25% swell creates 225 m³ loose. At 8 m³ per trip that is 29 loads; three trucks making nine trips each per shift require two shifts.

Which inputs determine excavation spoil haul trips and shifts?

The estimate first expands the excavated volume by the entered swell allowance, rounds up to whole truck loads, then estimates loads completed per shift from cycle time and productive shift minutes.

What does this estimate leave out?

Swell, volume capacity, and cycle time are user estimates. The model assumes similar repeat cycles and no queues; check truck payload, road access, disposal rules, and site conditions separately.

How do I use the Excavation spoil truck loads and fleet duration calculator?

Enter In-place excavation volume (m³), Loose-volume swell (%), Truck loose-volume capacity (m³), Average truck cycle (minutes), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Excavation spoil truck loads and fleet duration?

In-place excavation volume (m³) = 180; Loose-volume swell (%) = 25; Truck loose-volume capacity (m³) = 8; Average truck cycle (minutes) = 42; Available trucks = 3; Productive shift time (hours) = 8; Time utilization (%) = 80. Loose spoil volume: 225 m³ Truck trips required: 29 loads Trips per truck per shift: 9 trips Estimated hauling shifts: 2 shifts Total truck cycle time: 20.3 truck-hours Excavating 180 m³ with 25% swell creates 225 m³ loose. At 8 m³ per trip that is 29 loads; three trucks making nine trips each per shift require two shifts.

Method reference: FHWA earthwork swell guidance. FHWA describes swell as the increase from original cut volume to excavated/placed volume and recommends using field factors for similar material; the calculator keeps swell as an explicit estimate.