CalcWorldHub
Free online calculator · no signup

Laser cutting time from path length piercing count and feed rate calculator

Estimate programmed cutting time for a part from total laser path, pierce count, and cutting speed.

4,000 tools
Laser cutting time from path length piercing count and feed rate calculator — Total cut path length (m), Cutting speed (m/min), Pierce count and calculation method
Laser cutting time from path length piercing count and feed rate calculator: inputs and calculation method.

How to use this calculator

Estimate programmed cutting time for a part from total laser path, pierce count, and cutting speed.

  1. Enter Total cut path length (m), Cutting speed (m/min), Pierce count, Average pierce time (s), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Laser cutting time from path length piercing count and feed rate explained

This cycle estimate adds steady cutting travel, pierce time, and per-part setup or loading time. It assumes the entered feed rate applies across the full programmed path and does not model acceleration, corner slowdowns, material changes, or nested-part scheduling.

Steady cut time95s
Steady cut time: 95 s in the worked scenario.

Inputs, symbols, and units

path — Total cut path length (m)
Sum of all contour lengths at the selected thickness.
speed — Cutting speed (m/min)
Programmed steady cutting feed.
pierces — Pierce count
Number of pierce events. Enter a whole number.
pierceTime — Average pierce time (s)
Average non-cutting time per pierce.
setup — Load and setup time per part (s)
Part-specific setup and handling allowance.

Formula and method

Cycle time = 60L/v + Npierce tpierce + tsetup.

Cutting time uses total programmed path divided by steady feed. Pierce and per-part setup times are added in seconds.

A worked scenario

Total cut path length (m) = 3.8; Cutting speed (m/min) = 2.4; Pierce count = 24; Average pierce time (s) = 0.7; Load and setup time per part (s) = 18.

  • Steady cut time: 95 s
  • Piercing time: 16.8 s
  • Estimated cycle time: 129.8 s
  • Theoretical parts per hour: 27.734977 parts/h

A 3.8 m path at 2.4 m/min takes 95 seconds of cutting; 24 pierces and 18 seconds handling yield a 129.8 second estimate.

Assumptions and edge cases

Corner slowdown, acceleration, lead-ins, gas changes, sheet repositioning, and machine-specific cutting tables are excluded.

Reading the outputs

The main result is laser cutting cycle time; supporting outputs are labeled with their own units. Use the units shown beside each input and result.

Frequently asked questions

What does the laser cutting time from path length piercing count and feed rate calculate?

A 3.8 m path at 2.4 m/min takes 95 seconds of cutting; 24 pierces and 18 seconds handling yield a 129.8 second estimate.

Which inputs most affect laser cutting cycle time?

Cutting time uses total programmed path divided by steady feed. Pierce and per-part setup times are added in seconds.

Can this result replace a site-specific or measured value?

Corner slowdown, acceleration, lead-ins, gas changes, sheet repositioning, and machine-specific cutting tables are excluded.

How do I use the Laser cutting time from path length piercing count and feed rate calculator?

Enter Total cut path length (m), Cutting speed (m/min), Pierce count, Average pierce time (s), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Laser cutting time from path length piercing count and feed rate?

Total cut path length (m) = 3.8; Cutting speed (m/min) = 2.4; Pierce count = 24; Average pierce time (s) = 0.7; Load and setup time per part (s) = 18. Steady cut time: 95 s Piercing time: 16.8 s Estimated cycle time: 129.8 s Theoretical parts per hour: 27.734977 parts/h A 3.8 m path at 2.4 m/min takes 95 seconds of cutting; 24 pierces and 18 seconds handling yield a 129.8 second estimate.