How to use this calculator
Check the latest eight process readings against the four Western Electric supplementary control-chart rules.
- Enter Chart center line, Chart standard deviation (σ), Reading 1 (oldest), Reading 2, then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
The Western Electric rules look for unusual patterns in a Shewhart chart, not just a single point outside a three-sigma limit. This checker standardizes eight chronological measurements against a supplied center line and standard deviation, then reports which of the four common rules are met.
Inputs and units
centerLine— Chart center line- The mean or target center line for the charted statistic.
sigma— Chart standard deviation (σ)- Positive standard deviation corresponding to the chart's zone limits.
p1— Reading 1 (oldest)- Oldest of the eight chronological chart points.
p2— Reading 2- Second-oldest chart point.
p3— Reading 3- Third-oldest chart point.
p4— Reading 4- Fourth-oldest chart point.
p5— Reading 5- Fifth-oldest chart point.
p6— Reading 6- Sixth-oldest chart point.
p7— Reading 7- Seventh-oldest chart point.
p8— Reading 8 (newest)- Newest chart point in the eight-point window.
Formula
zᵢ = (xᵢ − center line)/σ. Rule 1: any |zᵢ| > 3. Rule 2: ≥2 of 3 consecutive z values >2 or <−2 on one side. Rule 3: ≥4 of 5 >1 or <−1 on one side. Rule 4: all 8 are on the same side of zero.
Method
Enter the chart center line, the standard deviation used for the chart limits, and the eight most recent subgroup statistics in chronological order. The calculator converts each reading to a z-score and evaluates the four rules in each applicable sliding window.
Worked example
With center line 100 and σ = 2, a reading of 107 has z = (107 − 100)/2 = 3.5 and triggers Rule 1. The remaining points are evaluated for the three run and zone rules.
Assumptions and limits
This is a supplemental signal check, not a control-chart design or a diagnosis of process cause. Use a stable, appropriate center line and standard deviation for the plotted statistic. Adding run rules increases sensitivity but can also increase false alarms; investigate signals with process context rather than treating them as proof of a cause.
Frequently asked questions
Which four rules are checked?
The checker tests one point beyond 3σ, two of three beyond 2σ on one side, four of five beyond 1σ on one side, and eight consecutive points on one side of the center line.
Do all readings need to be in chronological order?
Yes. Rules 2 through 4 depend on the sequence, so enter the oldest point first and the newest point last.
Does a signal prove that a process is out of control?
No. A signal prompts investigation. Additional rules can increase false alarms, and the chart limits must be appropriate for the process and statistic.
How do I use the Western Electric control chart rules checker?
Enter Chart center line, Chart standard deviation (σ), Reading 1 (oldest), Reading 2, then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Western Electric control chart rules checker?
With center line 100 and σ = 2, a reading of 107 has z = (107 − 100)/2 = 3.5 and triggers Rule 1. The remaining points are evaluated for the three run and zone rules.
Reference: NIST/SEMATECH control-chart rules and run signals. See our calculation methodology.