Scale daily variation across the lead-time window
For independent daily demand with a stable variance and a fixed lead time, the calculator uses σL = σd√L. σd is the standard deviation of demand in units per day, L is lead time in days, and σL is the standard deviation of the total units demanded during lead time. Independent variances add, so the variance over L days is Lσd²; taking the square root gives σd√L.
The square-root is the key distinction from multiplying an average by time. Mean demand accumulates linearly as dL, while independent random variation accumulates by the square root of the number of periods. The result is a measure of the width of the lead-time demand distribution under the model. It does not calculate a safety factor, a service level, or the mean demand.
Worked examples
Five days of daily variability
Inputs: Daily demand standard deviation 7 units/day; fixed lead time 5 days.
Calculation: σL = 7√5 = 15.6524758 units, displayed to four decimal places as 15.6525 units.
This is the spread of total demand across the five-day window, not its average or a safety-stock quantity.
Eight-day window with lower daily spread
Inputs: Daily demand standard deviation 4.5 units/day; fixed lead time 8 days.
Calculation: σL = 4.5√8 = 12.7279221 units, displayed as 12.7279 units.
The longer window increases the combined variation, but the increase follows the square-root scale under independence.
Prepare demand data at the same daily horizon
Estimate daily standard deviation from a consistent series of daily usage or forecast errors. The selected series should describe the same item and the same type of day that the lead-time input represents. If weekends are excluded from the demand history but counted in delivery time, align the series and the clock before applying the square-root rule. Do not enter a monthly standard deviation as though it were daily.
The formula assumes one daily variance repeats across the fixed number of days and that day-to-day demand errors are independent. A trend, autocorrelation, promotion cycle, or clustered demand can make that assumption weak. Where the forecast system provides a lead-time error distribution directly, use the uncertainty for that horizon rather than rescaling a daily standard deviation mechanically.
Interpret two lead-time examples
With σd = 7 units/day and L = 5 days, σL = 7√5 = 15.6525 units. The total demand over five days still has its own expected value, which requires the mean demand rate; it is not 15.65 units. This standard deviation says how far total demand may typically vary around that mean under the assumed distribution, not how many units to order.
With a daily standard deviation of 4.5 units and an eight-day lead time, σL = 4.5√8 = 12.7279 units. Doubling lead time from four to eight days increases spread by √2, not by two, if each day adds an independent equal variance. Doubling the daily standard deviation, by contrast, doubles the result because it scales directly with σd.
Know what the result can feed into
A fixed-lead-time safety-stock estimate can multiply σL by a positive normal factor z. A reorder point can then add that buffer to expected lead-time demand, dL. Those are separate steps and require more inputs than this calculator asks for. If z is intended to represent a cycle service target, choose it from the correct one-sided service probability; a fill rate is a different measure and is not determined by a standard-deviation result alone.
This tool permits a zero lead time and nonnegative daily spread, matching its evaluator. A zero lead time returns zero spread. For an actual replenishment policy, use the operational lead time in days; a rounded result may be easier to communicate but keep enough precision when it feeds another calculation.
Check the independence and lead-time assumptions
If adjacent days move together, the variance of their sum includes covariance terms. Positive correlation increases total spread beyond σd√L; negative correlation can reduce it. Similarly, variable lead time adds uncertainty even if daily demand is stable. The fixed-lead formula does not capture either effect. Iowa's inventory lecture shows the broader variance expression for random demand and random lead time; with fixed L, the demand-variance term simplifies to Lσd².
A useful validation is to collect historical demand totals for windows with the same lead-time length and compare their sample spread with the calculated estimate. Investigate differences in forecast bias, promotional weeks, lost sales, missing zero-demand days, or supplier delays. Do not tune the reported deviation merely to match a desired stock level; the service factor and the chosen customer-service measure belong in the next policy decision.