Purchase Requisition Approval Time: Measure the Review Cycle

An internal purchase request can pass through several approvals before it becomes authorized work. Measuring elapsed time helps teams see the pace of that review process, but a single mean hides variation and says little about where the delay occurred. This calculator summarizes decided requisitions using the total elapsed days and the number with a final decision.

Open calculator
Illustration of a purchase requisition moving from submission through review to final decision, with pending requests separated from decided requests.

Share this article

Total elapsed calendar days from submission to final decision divided by decided requisitions.
Use one start event, one final-decision event, and a consistent clock.

Be precise about the start and stop

The intended clock starts when a requisition is submitted and stops at its final decision. For this measure, divide total elapsed calendar days for decided requisitions by the number of decided requisitions. Both approvals and rejections are final decisions in the calculator’s description; it does not have a field that limits the denominator to approved requests only.

Oracle’s prebuilt metric describes requisition approval cycle time using the average difference between approval and submission dates, with a version-zero rule. That is a useful reference, but this calculator receives a total and a count, so it does not apply the version rule or inspect workflow revisions. State the event definition and revision treatment for your own cohort.

Enter totals in the right units

Total elapsed decision days may be fractional, for example when timestamps are converted to partial days. Requisitions with a final decision must be a positive whole count. The runtime accepts finite nonnegative total days up to its configured maximum and a positive safe integer count, then displays the mean to two decimal places.

Use calendar days if the elapsed total includes weekends and holidays. A business-hours measure needs different clock logic, work schedules, and units; it should not be described as this calculator’s output. The page does not infer dates or adjust for pauses, so any rules for waiting on requesters, budget holders, or suppliers must be settled before the total is prepared.

Pending requests change the interpretation

Only requisitions with a final decision enter the average. Recent requests still waiting for approval are excluded. If an organization reports only completed cases, the measure can fall while the backlog grows, because newer slow cases have not yet reached the stop event. Keep pending count and age visible beside the mean.

The calculator cannot tell whether the cohort is complete, whether each record was approved or rejected, or whether a long elapsed time came from one approver or several queues. Preserve individual submission and decision timestamps so the total can be audited and the process can be segmented by stage, request type, amount, or approval route.

Read the mean as a summary, not a diagnosis

A mean is the sum of all elapsed times divided by the count. One unusually long request can pull it upward; many fast decisions can offset several very slow ones. A median, percentile distribution, and count of overdue pending requests help show the shape of the work more clearly than one average.

When comparing departments or months, use consistent start and end events, calendar rules, and cohort assignment. Larger or higher-risk purchases may require additional review steps, so a longer average is not automatically evidence of poor performance. Compare like with like and interpret the time alongside control requirements and decision quality.

Make the cohort reproducible

Document the submission event, decision event, treatment of reopened or resubmitted requests, cohort date, and any paused intervals. Use one requisition as one observation unless your policy explicitly analyzes each approval stage separately. If a request is edited and resubmitted, retain its history and state whether the clock restarts or continues.

For a combined mean across teams, add their total elapsed days and decided-requisition counts, then divide once. Averaging team-level averages without weighting can give a tiny team the same influence as a large one. Keep the exact totals and counts in the report so a reviewer can reproduce the two-decimal display.

Worked examples

These examples use elapsed calendar days to final decision. Their averages include only decided requisitions; an open request backlog is not represented in either calculation.

A 28-requisition decision cohort

Inputs: 112 total elapsed calendar days across 28 requisitions with final decisions

Calculation: 112 ÷ 28 = 4.00 calendar days per decided requisition

The mean decision time is 4.00 calendar days. Pending requests should be reported separately.

A cohort with a longer average

Inputs: 135 elapsed calendar days across 30 decided requisitions

Calculation: 135 ÷ 30 = 4.5 calendar days per decision

The calculator displays 4.50 calendar days. The mean alone does not identify which workflow step caused delay.

Decided requisitions contribute elapsed days to the mean while pending requisitions remain in a separate backlog.
Keep open items visible beside the completed-case average.