How to use this calculator
Calculate CBR at 2.5 mm and 5.0 mm penetration from corrected test loads and their matching standard loads.
- Enter Corrected test load at 2.5 mm (kN), Standard reference load at 2.5 mm (kN), Corrected test load at 5.0 mm (kN), Standard reference load at 5.0 mm (kN). Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Enter the corrected test load and the matching standard reference load at each penetration depth. The two loads in a pair must use the same force unit. The calculator reports both ratios so they can be reviewed under the applicable laboratory or field test procedure.
Inputs and units
testLoad25— Corrected test load at 2.5 mm (kN)- Enter the corrected load measured at 2.5 mm penetration.
standardLoad25— Standard reference load at 2.5 mm (kN)- Enter the method-specified reference load for 2.5 mm penetration.
testLoad50— Corrected test load at 5.0 mm (kN)- Enter the corrected load measured at 5.0 mm penetration.
standardLoad50— Standard reference load at 5.0 mm (kN)- Enter the method-specified reference load for 5.0 mm penetration.
Formula
CBR (%) = 100 × corrected test load / standard reference load at the same penetration.
Method
Calculate the load ratio independently at 2.5 mm and 5.0 mm penetration. No result is selected for design or reporting because procedures and agency requirements govern test correction, repetition, and adoption of a value.
Worked example
Corrected loads of 12 kN and 18 kN against reference loads of 100 kN and 150 kN give CBR values of 12.00% at both 2.5 mm and 5.0 mm penetration.
Assumptions and limits
CBR is an indirect, procedure-dependent measure rather than a fundamental soil property. Results depend on specimen preparation, compaction, moisture, soaking, and corrected load readings. Use standard reference loads and reporting rules from the applicable method and agency; this calculation does not replace the test procedure or pavement design review.
Frequently asked questions
What does CBR compare?
It compares the test load at a prescribed penetration with the standard load required at that same penetration.
Can I use different force units in a pair?
No. Each corrected test load and its matching standard reference load must use the same force unit.
Which penetration result should I report?
Use the applicable test method and agency reporting rules. This calculator presents the 2.5 mm and 5.0 mm ratios separately and does not choose a design value.
How do I use the California Bearing Ratio (CBR) Calculator?
Enter Corrected test load at 2.5 mm (kN), Standard reference load at 2.5 mm (kN), Corrected test load at 5.0 mm (kN), Standard reference load at 5.0 mm (kN). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of California Bearing Ratio (CBR)?
Corrected loads of 12 kN and 18 kN against reference loads of 100 kN and 150 kN give CBR values of 12.00% at both 2.5 mm and 5.0 mm penetration.
Reference: technical reference. See our calculation methodology.