CalcWorldHub
Free online calculator · no signup

Cascade refrigeration interstage duty calculator

Size the intermediate heat exchange and combined compressor power of two coupled refrigeration stages.

4,000 tools
Cascade refrigeration interstage duty calculator — Low-stage cooling load (kW), Low-stage COP, High-stage COP and calculation method
Cascade refrigeration interstage duty calculator: inputs and calculation method.

How to use this calculator

Size the intermediate heat exchange and combined compressor power of two coupled refrigeration stages.

  1. Enter Low-stage cooling load (kW), Low-stage COP, High-stage COP. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Cascade refrigeration interstage duty explained

The low-stage condenser rejects both the low-stage cooling load and compressor work, so the high stage must remove their sum. This idealized cascade balance derives interstage duty and combined compressor power from the two entered COP values.

Overall cooling COP1.1429
Overall cooling COP: 1.142857 in the worked scenario.

Inputs, symbols, and units

L — Low-stage cooling load (kW)
Low-stage cooling load (kW). Enter the value for this state; the units shown are used without an unstated conversion.
cl — Low-stage COP
Low-stage COP. Enter the value for this state; the units shown are used without an unstated conversion.
ch — High-stage COP
High-stage COP. Enter the value for this state; the units shown are used without an unstated conversion.

Formula and method

WL=QL/COPL; Qcascade=QL+WL; WH=Qcascade/COPH; COPtotal=QL/(WL+WH).

The high-temperature evaporator must absorb the full low-temperature condenser duty, including low-stage compressor heat. Apply stage COP values at their actual operating temperatures.

A worked scenario

Low-stage cooling load (kW) = 20; Low-stage COP = 2; High-stage COP = 4.

  • Overall cooling COP: 1.142857
  • Low-stage work: 10 kW
  • High-stage work: 7.5 kW
  • Cascade exchanger duty: 30 kW

A 20 kW low-temperature load with lower-stage COP 2 passes 30 kW into the upper stage. Upper-stage COP 4 adds 7.5 kW power, so total power is 17.5 kW and the combined COP is only 1.14286.

Assumptions and edge cases

Steady cascade exchanger with no ambient heat leak, auxiliary loads or interstage temperature/property calculation.

Reading the outputs

Overall COP uses only the useful low-temperature load. Stage powers and intermediate duty are reported in kW.

Frequently asked questions

Can I average the two COP values?

No. The upper stage handles more heat than the useful cooling load.

Does the cascade exchanger reject heat outdoors?

Its modeled duty passes internally from the low stage to the high stage.

Where do I account for fans?

Add auxiliary power to total electrical demand outside this ideal stage balance.

How do I use the Cascade refrigeration interstage duty calculator?

Enter Low-stage cooling load (kW), Low-stage COP, High-stage COP. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Cascade refrigeration interstage duty?

Low-stage cooling load (kW) = 20; Low-stage COP = 2; High-stage COP = 4. Overall cooling COP: 1.142857 Low-stage work: 10 kW High-stage work: 7.5 kW Cascade exchanger duty: 30 kW A 20 kW low-temperature load with lower-stage COP 2 passes 30 kW into the upper stage. Upper-stage COP 4 adds 7.5 kW power, so total power is 17.5 kW and the combined COP is only 1.14286.