How to use this calculator
Measure scheduled workdays lost to weather within the selected construction reporting period.
- Enter Scheduled workdays lost to weather, Scheduled workdays. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Weather delay day rate compares scheduled construction workdays lost to qualifying weather with all scheduled workdays in the same period. Count a scheduled workday at most once even if several weather impacts occur that day.
Inputs and units
weatherLostWorkdays— Scheduled workdays lost to weather- Whole scheduled workdays lost under the project weather-impact rule.
scheduledWorkdays— Scheduled workdays- Whole scheduled workdays in the same reporting period, including affected days.
Formula
Weather delay day rate (%) = scheduled workdays lost to weather ÷ scheduled workdays × 100.
Method
Use the project calendar and weather-delay rule in effect for the selected period. Include weather-affected workdays in the scheduled-day denominator.
Worked example
Of 60 scheduled construction workdays, 12 are lost to qualifying weather. The weather delay day rate is 20.00%, with 48 scheduled workdays not lost to weather.
Assumptions and limits
This ratio does not determine contractual entitlement, critical-path impact, or excusable delay under a project agreement.
Frequently asked questions
Does a lost day require a full-day stoppage?
Apply the project’s consistent weather-impact rule, including any threshold for partial-day impacts.
Does this prove an excusable delay?
No. Contract terms, notice, critical path, and project records determine entitlement.
Should nonscheduled weekends count?
No. The denominator is scheduled workdays from the project calendar.
How do I use the Construction Weather Delay Day Rate Calculator?
Enter Scheduled workdays lost to weather, Scheduled workdays. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Construction Weather Delay Day Rate?
Of 60 scheduled construction workdays, 12 are lost to qualifying weather. The weather delay day rate is 20.00%, with 48 scheduled workdays not lost to weather.
Read our calculation methodology.