How to use this calculator
Measure milestones completed by baseline due dates among milestones due in the period.
- Enter Milestones completed by baseline date, Milestones due in period. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Enter the number of baseline milestones completed on or before their original due date and the total milestones due in the same reporting period. Include late or incomplete due milestones in the denominator.
Inputs and units
onTimeMilestones— Milestones completed by baseline date- Milestones due in this period that were completed on or before their original baseline date.
milestonesDue— Milestones due in period- All milestones due in the period under the selected baseline, including late and incomplete milestones.
Formula
Milestone on-time completion rate (%) = milestones completed by baseline due date ÷ milestones due in period × 100.
Method
Compare each completed milestone with its frozen baseline due date, then divide on-time completions by all milestones due in the reporting period.
Worked example
If 17 of 20 milestones due in a period were completed by their baseline dates, the on-time rate is 85.00%, with 3 late or incomplete.
Assumptions and limits
Define the baseline and reporting period before counting. Do not remove late or incomplete milestones from the denominator; exclude formally canceled milestones only under a consistently applied rule.
Frequently asked questions
What counts as on time?
A milestone is on time when it is completed on or before its original baseline due date.
Do incomplete milestones count?
Yes, if they were due in the reporting period under the chosen baseline.
Is this earned schedule variance?
No. This is a count-based cohort rate; earned schedule measures schedule position and time variance.
How do I use the Project Milestone On-Time Completion Rate Calculator?
Enter Milestones completed by baseline date, Milestones due in period. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Project Milestone On-Time Completion Rate?
If 17 of 20 milestones due in a period were completed by their baseline dates, the on-time rate is 85.00%, with 3 late or incomplete.
Read our calculation methodology.