How to use this calculator
Compute earliest/latest starts, total float, and project duration for a finish-to-start activity network.
- Enter Activity durations, Precedence edges as from>to, comma separated. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Activity network critical path and float explained
The forward pass finds earliest starts through the finish-to-start network; the backward pass finds latest starts from the project finish. Activities with zero total float form a critical path under the entered durations and precedence links.
Inputs, symbols, and units
d— Activity durations- Activity durations. Use comma-separated values in the stated order.
e— Precedence edges as from>to, comma separated- Precedence edges as from>to, comma separated.
Formula and method
DAG forward and backward longest-path passes
Topologically order the graph. Each earliest start is the maximum predecessor finish. Starting from project completion, reverse the order to find latest starts; latest minus earliest start is total float.
A worked scenario
Activity durations = 3, 4, 2, 5; Precedence edges as from>to, comma separated = 1>2, 1>3, 2>4, 3>4.
- Project duration: 12 time units
- Earliest starts: 0, 3, 3, 7
- Total floats: 0, 0, 2, 0
- Zero-float activity numbers: 1, 2, 4
Activity 4 waits for both activities 2 and 3. The path 1→2→4 takes 3+4+5=12 time units and determines the project duration.
Assumptions and edge cases
Activities use one-based indices, zero lags, unlimited resources, and a directed acyclic precedence graph.
Frequently asked questions
Can an activity have several predecessors?
Yes, add an edge for each dependency.
Are resource conflicts included?
No.
What happens if dependencies form a cycle?
The graph is rejected.
How do I use the Activity network critical path and float calculator?
Enter Activity durations, Precedence edges as from>to, comma separated. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Activity network critical path and float?
Activity durations = 3, 4, 2, 5; Precedence edges as from>to, comma separated = 1>2, 1>3, 2>4, 3>4. Project duration: 12 time units Earliest starts: 0, 3, 3, 7 Total floats: 0, 0, 2, 0 Zero-float activity numbers: 1, 2, 4 Activity 4 waits for both activities 2 and 3. The path 1→2→4 takes 3+4+5=12 time units and determines the project duration.
Read our calculation methodology.