Activity network critical path and float calculator

Compute earliest/latest starts, total float, and project duration for a finish-to-start activity network.

4,000 tools
Activity network critical path and float calculator — Activity durations, Precedence edges as from>to, comma separated and calculation method
Activity network critical path and float calculator: inputs and calculation method.

How to use this calculator

Compute earliest/latest starts, total float, and project duration for a finish-to-start activity network.

  1. Enter Activity durations, Precedence edges as from>to, comma separated. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Activity network critical path and float explained

The forward pass finds earliest starts through the finish-to-start network; the backward pass finds latest starts from the project finish. Activities with zero total float form a critical path under the entered durations and precedence links.

Project duration12time units
Project duration: 12 time units in the worked scenario.

Inputs, symbols, and units

d — Activity durations
Activity durations. Use comma-separated values in the stated order.
e — Precedence edges as from>to, comma separated
Precedence edges as from>to, comma separated.

Formula and method

DAG forward and backward longest-path passes

Topologically order the graph. Each earliest start is the maximum predecessor finish. Starting from project completion, reverse the order to find latest starts; latest minus earliest start is total float.

A worked scenario

Activity durations = 3, 4, 2, 5; Precedence edges as from>to, comma separated = 1>2, 1>3, 2>4, 3>4.

  • Project duration: 12 time units
  • Earliest starts: 0, 3, 3, 7
  • Total floats: 0, 0, 2, 0
  • Zero-float activity numbers: 1, 2, 4

Activity 4 waits for both activities 2 and 3. The path 1→2→4 takes 3+4+5=12 time units and determines the project duration.

Assumptions and edge cases

Activities use one-based indices, zero lags, unlimited resources, and a directed acyclic precedence graph.

Frequently asked questions

Can an activity have several predecessors?

Yes, add an edge for each dependency.

Are resource conflicts included?

No.

What happens if dependencies form a cycle?

The graph is rejected.

How do I use the Activity network critical path and float calculator?

Enter Activity durations, Precedence edges as from>to, comma separated. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Activity network critical path and float?

Activity durations = 3, 4, 2, 5; Precedence edges as from>to, comma separated = 1>2, 1>3, 2>4, 3>4. Project duration: 12 time units Earliest starts: 0, 3, 3, 7 Total floats: 0, 0, 2, 0 Zero-float activity numbers: 1, 2, 4 Activity 4 waits for both activities 2 and 3. The path 1→2→4 takes 3+4+5=12 time units and determines the project duration.