CalcWorldHub
Free online calculator · no signup

PERT fixed path deadline probability calculator

Approximate the chance that one specified serial activity path finishes by a deadline using three-point PERT moments.

4,000 tools
PERT fixed path deadline probability calculator — Optimistic durations, Most likely durations, Pessimistic durations and calculation method
PERT fixed path deadline probability calculator: inputs and calculation method.

How to use this calculator

Approximate the chance that one specified serial activity path finishes by a deadline using three-point PERT moments.

  1. Enter Optimistic durations, Most likely durations, Pessimistic durations, Deadline for this fixed serial path. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

PERT fixed path deadline probability explained

Approximate the completion probability for one fixed serial path with independent PERT activity durations.

Approximate fixed-path deadline probability0.9505
Approximate fixed-path deadline probability: 0.95051992 in the worked scenario.

How the calculation works

Normal approximation to sum of PERT activity durations

For each activity, PERT mean is (a+4m+b)/6 and variance is ((b−a)/6)²; independent path means and variances are summed. Independent activities and a fixed path; path switching and skewed completion distributions can make the normal approximation inaccurate..

Set up the calculation

a — Optimistic durations
Best-case duration for each activity on the fixed path, listed in matching activity order.
m — Most likely durations
Most likely duration for each corresponding activity; position i pairs with the optimistic and pessimistic values at i.
b — Pessimistic durations
Worst-case duration for each activity, listed in the same order and with the same number of entries.
d — Deadline for this fixed serial path
Completion-time threshold compared with the approximate normal distribution of the summed activity durations.

Limits of this model

Independent activities and a fixed path; path switching and skewed completion distributions can make the normal approximation inaccurate.

Check this example

Optimistic durations = 2, 3; Most likely durations = 4, 5; Pessimistic durations = 8, 9; Deadline for this fixed serial path = 12.

  • Approximate fixed-path deadline probability: 0.95051992
  • Expected path duration: 9.666667 time units
  • Path standard deviation: 1.414214 time units

The two activities give expected path duration 9.6667 time units and standard deviation √2; the normal approximation gives about 0.95052 probability by time 12.

Interpreting the result

This probability summarizes only the selected serial path under a normal approximation; it is not a full project completion probability when paths can switch or activities depend on one another.

Frequently asked questions

Does this compute the critical path?

No, supply activities from the path being evaluated.

Why not treat it as an exact project probability?

Other paths may become critical and durations need not be normal.

Must optimistic ≤ most likely ≤ pessimistic?

Yes.

How do I use the PERT fixed path deadline probability calculator?

Enter Optimistic durations, Most likely durations, Pessimistic durations, Deadline for this fixed serial path. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of PERT fixed path deadline probability?

Optimistic durations = 2, 3; Most likely durations = 4, 5; Pessimistic durations = 8, 9; Deadline for this fixed serial path = 12. Approximate fixed-path deadline probability: 0.95051992 Expected path duration: 9.666667 time units Path standard deviation: 1.414214 time units The two activities give expected path duration 9.6667 time units and standard deviation √2; the normal approximation gives about 0.95052 probability by time 12.