Ask about one fixed serial path
A fixed path is a sequence of tasks that must occur one after another. The calculator treats the entered tasks as that path, so the order and list membership should reflect the schedule logic you want to assess. If tasks overlap, can branch, or may become critical under different outcomes, a single summed path does not represent the whole project network.
Align the three-point task lists
Enter equal-length lists of optimistic, most-likely, and pessimistic durations, plus a deadline in the same time unit. Each row position represents one task, and the three lists must align in task order. For each task the estimates must be nonnegative and ordered O≤M≤P. The form checks list alignment and ordered estimates, but the user must ensure the selected path is valid.
Sum expected durations and variances
For each activity, the expected time is (O+4M+P)/6 and the PERT variance is ((P−O)/6)². The fixed-path mean is the sum of activity means; under the tool’s independence assumption, path variance is the sum of the activity variances. Taking the square root gives path standard deviation. The deadline is then standardized against that mean and spread.
Translate the deadline to a z score
The reported probability uses a normal cumulative approximation: z=(deadline−path mean)/path standard deviation, followed by the standard normal cumulative distribution. A deadline equal to the expected duration corresponds to approximately half the normal area. Moving the deadline earlier or later shifts the standardized threshold, but the approximation does not make every task duration normally distributed.
Interpret the probability with care
A fixed-path result answers a conditional question: assuming the chosen serial path, input estimates, independence, and approximation, how much modeled probability lies before the deadline? It does not identify the critical path, account for resource leveling, or compare alternative routes. Label the result as an approximation and state the path scope in any schedule note.
The normal tail is a smooth approximation to an accumulated distribution; actual task durations cannot be negative and may be lumpy or right-skewed. If the calculated path mean is short relative to its uncertainty, this shape mismatch matters more. Treat the probability as a model output for comparison, not as a statistical guarantee, and avoid excessive decimal precision when the estimates themselves are rough judgments.
Worked examples
The path totals use full precision; the displayed probability is rounded after the normal-CDF calculation.
A two-task path with a twelve-day deadline
Inputs: Task estimates (O,M,P) = (2,4,8) days and (3,5,9) days; deadline = 12 days.
Calculation: Path mean = 26/6 + 32/6 = 9.666667 days; variance = 1² + 1² = 2 days²; σ = √2 = 1.414214 days; z = (12−9.666667)/1.414214 ≈ 1.6499; P(T≤12) ≈ 0.95051992.
The fixed-path normal approximation gives about 95.05% by the stated deadline.
A tighter deadline on a similar path
Inputs: Task estimates (O,M,P) = (1,3,7) days and (4,6,10) days; deadline = 10 days.
Calculation: Path mean = 20/6 + 38/6 = 9.666667 days; variance = 1² + 1² = 2 days²; σ = √2 = 1.414214 days; z = (10−9.666667)/1.414214 ≈ 0.2357; P(T≤10) ≈ 0.59316814.
The approximate chance of finishing by ten days is about 59.32% under this fixed-path model.
Limits of a fixed-path approximation
Use the calculation to compare a few clearly defined schedule scenarios or to decide where better estimates would help. A small change in an endpoint can alter both the mean and spread. Retaining the individual task estimates makes it possible to see whether a probability change comes from a shifted expected duration, a wider uncertainty range, or a different path definition.
PERT path approximations can understate schedule risk at converging paths and omit correlations between tasks. Calendar constraints, lags, resource limits, rework loops, external approvals, and path switching are not modeled. If those effects matter to the commitment, use a schedule network with risk simulation or another method designed for the full dependency structure.