Project management calculator guides

Explore 12 practical guides with worked examples, clear assumptions, and direct links to the calculators they explain.

Browse by topic

Showing 1–12 of 12 articles

A sequence of work items is interrupted by a marked blocker, separating blocked intervals from total elapsed time.
Project management

Blocked Work Fraction: Measure Time Spent Waiting on a Blocker

Compare accumulated blocked time with elapsed work-item time for the same cohort, while keeping task counts and blocker causes separate.

Read article
A project timeline shows an approved baseline marker and a later actual finish, with the gap representing duration variance.
Project management

Project Duration Variance: Compare Actual Time with a Baseline

Compare a completed project’s elapsed duration with its approved baseline using the same calendar and time-unit rules.

Read article
Two aligned project budget bars compare an approved estimate with a higher final actual cost.
Project management

Project Cost Estimate Variance: Compare Final Cost with the Approved Estimate

Calculate the signed difference between final project cost and an approved estimate, with checks for scope, currency, contingency, and cost basis.

Read article
A change-control board reviews a request and records a decision, with approved and other final outcomes separated.
Project management

Project Change Request Approval Rate: Define the Decision Cohort

Calculate approved change requests as a share of decided requests and report pending items separately from the approval ratio.

Read article
A calendar timeline shows a change request submitted, reviewed over elapsed days, and finally decided.
Project management

Project Change Request Decision Time: Calculate Mean Calendar Days

Calculate the mean elapsed calendar days from change-request submission to a final decision and keep pending cases visible outside the completed cohort.

Read article
A project risk register action is checked against its due date, separating completed-on-time actions from the remainder.
Project management

Project Risk Response On-Time Rate: Track Actions Due in a Cohort

Measure risk responses completed on or before their due date among actions due in the same reporting cohort, while keeping response effectiveness separate.

Read article
A project time-cost chart slopes upward from a normal-duration endpoint to a shorter crash-duration endpoint.
Project management

Project Crashing Cost Slope: Compare Cost per Time Saved

Calculate incremental direct cost per unit of activity duration reduced between normal and crash endpoints.

Read article
A PERT duration diagram weights the most-likely estimate four times and adds one optimistic and one pessimistic estimate.
Project management

PERT Expected Duration: A Weighted Estimate from Three Times

Estimate an activity’s PERT expected duration by weighting the most-likely time more heavily than the optimistic and pessimistic bounds.

Read article
A PERT range is divided by six to estimate standard deviation and squared to produce duration variance.
Project management

PERT Duration Variance: Quantifying a Three-Point Estimate

Calculate PERT activity-duration variance from the optimistic and pessimistic estimates using the conventional one-sixth range approximation.

Read article
A duration range between optimistic and pessimistic estimates is divided by six to show PERT standard deviation.
Project management

PERT Duration Standard Deviation: Interpreting Time Uncertainty

Estimate a PERT activity’s duration standard deviation as one sixth of its optimistic-to-pessimistic range.

Read article
A fixed serial task path produces an expected duration and spread that are compared with a deadline threshold.
Project management

PERT Deadline Probability for a Fixed Path: A Normal Approximation

Estimate the probability that a fixed serial path finishes by a chosen deadline using PERT duration estimates and a normal approximation.

Read article
A PERT weighting diagram highlights four of six equal weight units assigned to the most-likely duration.
Project management

PERT Most-Likely Estimate Weight: Why the Middle Case Counts Four Times

Calculate the most-likely estimate’s weighted contribution, four sixths of M, in the standard PERT expected-duration formula.

Read article