Set the actual and baseline boundaries
Choose one project start and one finish rule, then apply it to both durations. For example, count from authorization to operational handover, or from mobilization to acceptance; do not use the first rule for actual time and the second for the plan. The actual duration must be nonnegative, and the approved baseline duration must be positive.
Use the same unit on both inputs: calendar days with calendar days, or weeks with weeks. If the project calendar excludes weekends or planned shutdowns, that treatment must match in both figures. A baseline can be updated through a formal process, but the comparison should identify which approved version is being assessed. Keep both baselines distinct for change control.
Calculate the signed difference and relative change
The calculator reports duration variance = actual duration − baseline duration. It also reports percent variance = (actual − baseline) ÷ baseline × 100. For 20 actual weeks and a 16-week baseline, the difference is +4 weeks and the relative variance is 4 ÷ 16 × 100 = +25%. The denominator is the approved baseline, so the percentage expresses how large the difference is relative to the plan.
A positive result means actual elapsed time exceeded the baseline; a negative result means it finished sooner. The sign is intentionally retained. This calculation is not earned value schedule variance, which uses earned value concepts and a different basis. If you need schedule performance through an in-progress status date, use an appropriate schedule analysis rather than treating a finished-duration difference as a forecast.
Worked examples
Completed four weeks late
Inputs: Actual elapsed duration = 20 weeks; approved baseline duration = 16 weeks.
Calculation: Variance = 20 − 16 = +4 weeks. Percent variance = 4 ÷ 16 × 100 = +25%.
The project took four weeks longer than the selected baseline, a 25% positive duration variance.
Completed ahead of the baseline
Inputs: Actual elapsed duration = 11 weeks; approved baseline duration = 12 weeks.
Calculation: Variance = 11 − 12 = −1 week. Percent variance = −1 ÷ 12 × 100 = −8.333…%, or −8.33% to two decimal places.
The actual duration was one week shorter than baseline; the result is negative because actual time was lower.
Make a fair comparison across projects
For a portfolio view, separate projects by scope, scale, delivery approach, and calendar rules. A two-week slip can be 20% of a short project but less than 1% of a multi-year program. Both absolute time and relative variance matter, and the percentage should not be ranked without context. GAO schedule guidance emphasizes maintaining a usable baseline and actual schedule data; the calculator only performs the stated arithmetic comparison.
Keep start and finish dates, baseline duration, actual duration, and any approved scope or calendar change together. A project that adds a major deliverable may be compared with the original plan to show total change, or with a formally revised baseline to assess performance after the change. Label which question the comparison answers instead of silently substituting a revised target.
Interpret the number without assigning a cause
A +4-week variance says the project finished four weeks beyond the selected baseline. It does not identify critical-path delay, resource shortages, rework, scope changes, or waiting for a decision. Several causes can overlap, and work on noncritical tasks may not move the final completion date. Use schedule records and change history to investigate rather than inferring a cause from the variance alone.
A shorter-than-baseline finish is not automatically a success if scope was removed, acceptance criteria changed, or quality work moved after the recorded end date. Verify that actual completion includes the work the baseline promised. If the project remains active, do not enter elapsed-to-date as “actual duration” and interpret the output as a final overrun; the tool has no status-date or remaining-work input.
Check the arithmetic and document the rule
Recompute the absolute difference first, then divide that difference by the baseline. A spreadsheet check can use `=actual-baseline` and `=(actual-baseline)/baseline`; format only the second result as a percentage. Confirm that the same units appear in both duration fields and that the baseline is not zero. Rounding the percentage for display does not change the underlying time difference.
For a review note, preserve the baseline version, start/finish definitions, actual and planned durations, and the result’s sign. The calculator reports two values only: a time-unit difference and a percentage. It does not build a schedule, calculate critical path, determine a completion date, or recommend a recovery plan. Those decisions require the project’s detailed schedule and constraints.