Project Change Request Decision Time: Calculate Mean Calendar Days

Mean change-request decision time is the sum of elapsed calendar days from submission to final decision divided by the number of decided requests. If nine decided requests accumulated 45 calendar days, the mean is five days. This average is easy to check, but it can hide one very long review and excludes pending requests unless they have a final outcome under the chosen process.

Open calculator
A calendar timeline shows a change request submitted, reviewed over elapsed days, and finally decided.

Share this article

Summed elapsed calendar days divided by decided requests gives mean decision time.
Only decisions represented in the accumulated duration belong in the denominator.

Choose the request population

Define which requests are included and what counts as a final decision. Approved and rejected cases usually have a clear outcome, while requests awaiting more information may still be pending. The calculator expects total elapsed calendar days and a positive whole count of decided requests. Sum elapsed duration from each submission to its final decision for that same cohort.

Calendar days include weekends and holidays. If your board reports working days, convert and label the measure consistently rather than calling it calendar days. Use one timestamp convention for submission and decision—such as the date the request enters the formal log and the date the authorized decision is recorded. Withdrawn or superseded requests need an explicit inclusion rule.

Calculate the mean elapsed time

The formula is mean decision time = total elapsed calendar days ÷ decided requests. With 45 accumulated days across nine decisions, 45 ÷ 9 = 5 calendar days. The result is arithmetic mean duration, not median and not a service-level percentile. The source calculator returns only this mean and does not accept a pending count or due-date target.

When there is one 20-day decision and four 1-day decisions, the average is (20 + 1 + 1 + 1 + 1) ÷ 5 = 4.8 days, even though four of five decisions took one day. Retain individual durations or add median and percentile reporting if the long tail matters. A mean alone does not show how many cases exceeded a review target.

Worked examples

Nine completed decisions

Inputs: The elapsed times for nine decided requests sum to 45 calendar days.

Calculation: Mean decision time = 45 ÷ 9 = 5 calendar days.

The completed cohort averaged five calendar days from submission to final decision.

Thirteen decisions in another cohort

Inputs: The elapsed calendar-day totals for 13 final decisions sum to 52 days.

Calculation: 52 ÷ 13 = 4 calendar days per decision on average.

The mean is four days; the cohort’s pending queue and duration distribution are still needed to describe the full process.

Each request runs from submission to a final recorded decision, and the completed elapsed days are averaged.
Use consistent submission and decision timestamps.

Keep unfinished requests in view

Completed-case mean time can look shorter when slow cases remain pending. Report the number of pending requests, their age distribution, and the date through which the cohort was observed alongside the mean. Do not assign zero days to unresolved cases; zero would falsely state that a decision occurred immediately and distort the average.

If a request is reopened after a decision, choose whether the metric ends at the first final decision or the final resolution after reopening. Apply that rule consistently. Long pauses caused by missing information may be part of total calendar elapsed time if the request remains open; if the organization pauses its clock, document and subtract paused intervals explicitly before totaling.

Use the mean to improve review flow

Break down elapsed time by request type, impact, review path, or board cycle only when each category has enough cases to be meaningful. A slower mean may reflect a new approval route or a more complete analysis rather than inefficient review. Inspect the timestamps and rationale before drawing a conclusion, especially after a policy or scope change.

For a before-and-after comparison, keep the submission and decision events, calendar-day rule, treatment of withdrawals, and pending-case cutoff stable. A decrease in mean can result from faster decisions, but also from excluding harder cases or changing the cohort. Pair the metric with request volume and outcome quality so speed is not mistaken for sound governance.

Reconcile durations to the log

For a sample of requests, recompute calendar-day differences from the recorded dates and sum them. Confirm the count of decided requests equals the items represented in that sum. If one request has no valid final timestamp, do not silently add it to the denominator. Use a spreadsheet average as a spot check, preserving the unrounded total and count for review.

The output is a mean duration in calendar days. It does not estimate the next decision date, model the waiting queue, or report the percentage meeting a turnaround target. To evaluate a target, count requests whose actual decision date met the target and define how pending cases are treated. The approval-rate calculator is a separate outcome ratio and does not measure elapsed time.