Define which requests count as decided
Choose a cohort with a clear rule, such as all requests that received a final decision during a quarter. The numerator includes requests approved in that cohort; the denominator includes those approved or rejected in the same cohort. Pending, withdrawn, deferred for more information, and duplicate records need explicit treatment. If “deferred” is not final under the project’s process, do not count it as rejected.
The calculator takes whole-number counts, requires at least one decided request, and prevents approved requests from exceeding the decided total. The second result is decided requests not approved, which can include rejections or other non-approval outcomes depending on the organization’s decision taxonomy. Keep the underlying disposition categories if those distinctions matter.
Calculate the approval percentage
The formula is approval rate (%) = approved decided requests ÷ all decided requests × 100. With 18 approved and 24 decided, 18 ÷ 24 × 100 = 75%. The complement is 24 − 18 = 6 decided requests not approved. State the cohort dates and denominator definition whenever sharing a percentage.
The ratio is sensitive to which cases entered the decision cohort. If managers decide only straightforward requests while complex requests remain pending, the rate can look high even though the full submitted queue has a different mix. A separate pending count and aging measure help prevent the approval rate from being mistaken for a share of all submissions.
Worked examples
One review cohort
Inputs: Eighteen change requests were approved out of 24 requests with final decisions.
Calculation: 18 ÷ 24 × 100 = 75%. Decided requests not approved = 24 − 18 = 6.
Three quarters of the requests in this decided cohort were approved; pending requests are not included.
A smaller quarterly cohort
Inputs: Fourteen of 20 change requests reached a final decision and were approved.
Calculation: 14 ÷ 20 × 100 = 70%. Six decided requests were not approved.
The approval rate is 70%; compare the 14/20 counts and pending queue alongside the rate.
Read the rate as a process description
A high rate is not automatically good: it can mean requests are well aligned with project goals, or that review criteria are too permissive. A low rate can reflect careful control, poor request quality, or a mismatch between scope and the approved plan. Interpret the result with decision rationale, impact analysis, and change-control policy rather than treating an arbitrary percentage as a target.
For decision quality, review the effects on requirements, cost, schedule, risk, and acceptance criteria. PMI describes change control roles and documented decisions; the calculator only counts the outcomes defined for your cohort. It does not assess whether the approved requests were implemented, whether rejected requests were justified, or whether the project baseline was updated correctly.
Compare periods without distorting the cohort
Use stable rules for when a request is submitted, when its final decision is recorded, and how reopened or superseded requests are handled. A cohort by decision date measures current board dispositions; a cohort by submission date may require following each request until outcome. These can produce different rates when pending work crosses period boundaries.
Compare counts as well as percentages. A 75% rate from four decisions is less stable than the same rate from 400 decisions. If the request volume is small, report the numerator and denominator instead of emphasizing tiny percentage changes. Avoid adding repeated decisions for one request as if each were a unique request unless the metric explicitly counts decision events.
Audit the request log
Check a sample of records against the final decision field and verify that each counted request belongs to the selected cohort exactly once. Reconcile approved plus not approved to total decided; pending records should reconcile separately to the submitted queue if that is the reporting question. Keep the report filter or export so the count can be reproduced later.
This calculator has no input for pending requests, meeting frequency, decision time, scope impact, or risk. If review latency is the concern, measure elapsed calendar days from submission through final decision in a separate cohort and include pending-age reporting. If cost or schedule impact is the concern, compare approved baselines and actuals with matching scope rather than inferring impact from an approval rate.