PERT Duration Variance: Quantifying a Three-Point Estimate

PERT duration variance summarizes the spread implied by the optimistic and pessimistic estimates. It does not change the expected duration and it does not measure variance in observed project outcomes. The result can support a fixed-path planning calculation when the underlying assumptions are suitable and the activity estimates use one consistent time unit.

Open calculator
A PERT range is divided by six to estimate standard deviation and squared to produce duration variance.

Share this article

The optimistic-to-pessimistic range is converted into a standard deviation and variance.
Range becomes squared spread

What PERT variance describes

The two endpoints carry the uncertainty information for this shortcut. A wider plausible duration range produces a larger variance, while the most-likely estimate does not appear in this particular formula. That does not mean the central estimate is unimportant; it means this approximation represents activity spread from the range between the low and high points.

Compare the two duration bounds

Enter an optimistic duration O and a pessimistic duration P for the same activity, using the same unit. Both should be nonnegative, with P at least as large as O. A range that crosses different definitions of work, staffing, or elapsed time is not a meaningful input. Keep the input units together so the variance is expressed in the square of that unit.

Square the range divided by six

The conventional PERT estimate is Var(T) = ((P−O)/6)^2. First divide the duration range by six to estimate the activity standard deviation, then square it. Squaring makes variance grow quadratically with the range: doubling the O-to-P spread quadruples the variance. This relationship is why rough endpoints deserve a reasoned basis rather than casual stretching.

Keep variance units squared

Variance is not duration. If the inputs are days, the variance is days squared. To return to an intuitive duration scale, take the square root; that standard deviation is (P−O)/6. Do not add a variance directly to an expected duration, and do not label it as a probability. Use each statistic only in formulas that call for that quantity.

Use it with a compatible mean

On a fixed serial path, an analyst may sum activity variances under the model’s independence assumptions and then take the square root for path standard deviation. That path statistic can be used in a further deadline approximation, but it depends on more than this one calculation. Parallel tasks, critical-path changes, and dependencies need schedule-network treatment.

Do not confuse variance among task durations with uncertainty in the estimated endpoints themselves. If O and P are weak judgments, the calculated variance is precise arithmetic on uncertain inputs, not proof that the risk has been measured accurately. A sensitivity check can show how much the output changes when either endpoint is revised, while preserving the distinction between input uncertainty and the model’s range-based variance.

For two activities with the same expected duration, a larger variance signals a wider modeled range under this approximation, but it does not say which task is more likely to overrun a particular date. That question also depends on where the deadline sits relative to the mean and on the distributional assumptions. Keep variance as a building block, then use a deadline method that matches the decision instead of ranking risk by variance alone.

Worked examples

The one-sixth range is calculated before squaring, and the resulting unit is squared duration.

An eight-day optimistic-to-pessimistic range

Inputs: Optimistic O = 3 days; pessimistic P = 11 days.

Calculation: σ = (P−O) ÷ 6 = (11−3) ÷ 6 = 1.3333 days; Var(T) = σ² = 1.3333² ≈ 1.7778 days².

The conventional PERT activity variance is about 1.7778 days squared.

A twelve-day range

Inputs: Optimistic O = 2 days; pessimistic P = 14 days.

Calculation: Var(T) = ((14−2) ÷ 6)² = 2² = 4 days².

The wider range yields a variance of 4 days squared.

The PERT variance is the square of the duration range divided by six.
Activity variance

Limitations of a range-based spread

A useful estimate log records the source of each endpoint, the date of the estimate, and what “optimistic” and “pessimistic” mean for the task. If new evidence narrows or widens the plausible range, update both points rather than changing variance directly. This keeps the uncertainty summary traceable to the assumptions that produced it.

The formula is a conventional PERT approximation, not a statistical estimate from a duration sample. It assumes a particular relationship between the range and spread and does not test that relationship. Risk correlations, path convergence, resource limits, and skewed or multi-modal outcomes can make real project uncertainty differ substantially.