CalcWorldHub
Free online calculator · no signup

Wright cumulative average learning curve calculator

Estimate cumulative average labor and total labor under Wright’s learning-curve convention.

4,000 tools
Wright cumulative average learning curve calculator — First-unit labor hours, Cumulative-average learning rate per doubling (%), Cumulative units produced and calculation method
Wright cumulative average learning curve calculator: inputs and calculation method.

How to use this calculator

Estimate cumulative average labor and total labor under Wright’s learning-curve convention.

  1. Enter First-unit labor hours, Cumulative-average learning rate per doubling (%), Cumulative units produced. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Wright cumulative average learning curve explained

Wright’s cumulative-average model applies the learning percentage to average labor hours per unit whenever cumulative output doubles. The power-law exponent converts that doubling rule into an estimate for any entered cumulative quantity; it is not a unit-by-unit Crawford curve.

Inputs, symbols, and units

a — First-unit labor hours
First-unit labor hours.
r — Cumulative-average learning rate per doubling (%)
Cumulative-average learning rate per doubling (%).
n — Cumulative units produced
Cumulative units produced. Enter a whole number.

Formula and method

a*pow(n,log10(r/100)/log10(2))

The entered percentage applies to cumulative average time each time quantity doubles; it is not the individual-unit Crawford convention.

A worked scenario

First-unit labor hours = 10; Cumulative-average learning rate per doubling (%) = 80; Cumulative units produced = 16.

  • Cumulative average labor: 4.096 hours/unit
  • Total cumulative labor: 65.536 hours

An 80% rate gives exponent log₂(0.8)≈−0.321928. Sixteen units are four doublings, so average labor is 10×0.8⁴=4.096 hours/unit and total cumulative labor is 16×4.096=65.536 hours.

Assumptions and edge cases

The entered percentage applies to cumulative average time each time quantity doubles; it is not the individual-unit Crawford convention.

Frequently asked questions

What does an 80% rate mean?

Cumulative average time becomes 80% of its previous value after each doubling.

Is the result time for unit n?

No, it is average time through unit n.

Can rate exceed 100%?

This learning-only version does not model deterioration.

How do I use the Wright cumulative average learning curve calculator?

Enter First-unit labor hours, Cumulative-average learning rate per doubling (%), Cumulative units produced. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Wright cumulative average learning curve?

First-unit labor hours = 10; Cumulative-average learning rate per doubling (%) = 80; Cumulative units produced = 16. Cumulative average labor: 4.096 hours/unit Total cumulative labor: 65.536 hours An 80% rate gives exponent log₂(0.8)≈−0.321928. Sixteen units are four doublings, so average labor is 10×0.8⁴=4.096 hours/unit and total cumulative labor is 16×4.096=65.536 hours.