CalcWorldHub
Free online calculator · no signup

Concurrent project resource demand calculator

Identify peak simultaneous resource demand for a fixed schedule.

4,000 tools
Concurrent project resource demand calculator — Task start times, Task durations, Resource units per task and calculation method
Concurrent project resource demand calculator: inputs and calculation method.

How to use this calculator

Estimate peak concurrent project demand from task start, duration, and resource units. The timeline uses half-open intervals and reports the first peak time.

  1. Enter Task start times, Task durations, Resource units per task. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Calculation guide

Concurrent project resource demand explained

Use Task start times with Task durations to reproduce the sample calculation, then review the stated limits before carrying the result into another scenario.

Peak resource demand5resource units
Peak resource demand: 5 resource units in the worked scenario.

Inputs, symbols, and units

s — Task start times
Task start times. Use comma-separated values in the stated order.
d — Task durations
Task durations. Use comma-separated values in the stated order.
r — Resource units per task
Resource units per task. Use comma-separated values in the stated order.

Formula and method

Sweep start and finish events on half-open intervals

Symbols use the input definitions below. Constant resource demand during each task; intervals include the start and exclude the finish.

A worked scenario

Task start times = 0, 2, 4; Task durations = 4, 3, 2; Resource units per task = 2, 3, 1.

  • Peak resource demand: 5 resource units
  • First time peak begins: 2 time units

This scenario uses the stated units and assumptions. Displayed values are rounded only after calculation.

Assumptions and edge cases

Constant resource demand during each task; intervals include the start and exclude the finish. This reports load rather than automatically leveling it.

Frequently asked questions

Can a task finish when another starts?

Yes, the finishing task no longer contributes at that instant.

Are fractional resource units allowed?

Yes, for capacity shares.

Does it move tasks?

No.

How do I use the Concurrent project resource demand calculator?

Enter Task start times, Task durations, Resource units per task. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Concurrent project resource demand?

Task start times = 0, 2, 4; Task durations = 4, 3, 2; Resource units per task = 2, 3, 1. Peak resource demand: 5 resource units First time peak begins: 2 time units This scenario uses the stated units and assumptions. Displayed values are rounded only after calculation.