Earned value schedule variance calculator

Compare earned value with planned value to quantify schedule variance in the project’s chosen value units. Enter the values below to calculate a clear estimate and see the method.

A better way to figure it out
Clear
inputs.
∑
Clear result · useful details
Free calculatorNo signup ✓

Related calculators

Browse project management tools →

Earned value schedule variance calculator — Earned value (EV), Planned value (PV) and calculation method
Earned value schedule variance calculator: inputs and calculation method.
Free calculator guide

How to use the Earned value schedule variance calculator

Compare earned value with planned value at the same status date. The result is a budget-value measure of schedule performance, not a calendar-time estimate.

Inputs and units

Enter earned value and planned value for the same status date and in the same currency or budget units.

Formula and method

Schedule variance = EV − PV.

Schedule variance is EV−PV in value units; it is not a count of calendar days.

Worked example

EV of $52,000 minus PV of $50,000 gives a positive $2,000 variance.

Reading the result

A positive EV−PV means more budgeted work value was earned than planned at the status date; a negative value means less. The result is value, not days.

Assumptions and limitations

Use values from the same approved baseline, scope, and status date. Schedule variance alone does not show critical-path impact or the number of days of delay.

Sources and interpretation

The U.S. Department of Energy defines schedule variance as EV−PV and describes the sign against planned work. GAO explains that schedule variance is expressed in budget units, not time, and should be assessed with critical-path information. U.S. Department of Energy — EVM Module 6; U.S. GAO — Cost Estimating and Assessment Guide, Earned Value Management.

Frequently asked questions

How do I calculate earned value schedule variance?

Schedule variance = EV − PV. The worked example shows how the inputs map to the result.

What units does schedule variance use?

EV−PV has the same value units as the earned-value inputs, usually currency or budget units. It is not a number of calendar days.

Does a positive schedule variance mean the project is a certain number of days early?

No. Positive SV means earned value exceeds planned value at the status date; the amount is in value units and does not directly convert to calendar time.

How do I use the Earned value schedule variance calculator?

Enter Earned value (EV), Planned value (PV). Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Earned value schedule variance?

EV of $52,000 minus PV of $50,000 gives a positive $2,000 variance.