PERT expected task duration calculator

Give the most-likely duration four times the weight of either endpoint in a simple three-point estimate.

A better way to figure it out
Simple
inputs.
Clear result · useful details
3, 5, and 11 days5.67 days

Calculator

4,000 tools
PERT expected task duration calculator — Project management inputs and calculation method
PERT expected task duration calculator: inputs and calculation method.

How to use this calculator

Calculate a PERT weighted duration estimate from optimistic, most-likely, and pessimistic task durations.

  1. Complete the labeled inputs for PERT expected task duration. Use the units requested by each field, then read the displayed result alongside the method and limits below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Project management calculation guide

A weighted three-point estimate

Formula and method

PERT expected duration = (optimistic + 4 × most likely + pessimistic) ÷ 6. Enter all three estimates for the same task and in the same unit.

Worked example

For 3 optimistic days, 5 most-likely days, and 11 pessimistic days, (3 + 4×5 + 11) ÷ 6 = 34/6 ≈ 5.67 days.

Interpreting the result

The weighted estimate is a planning input for one activity. A project end date also depends on dependencies, resource limits, parallel work, and schedule risk.

Assumptions and limits

Three-point estimates depend on informed bounds and the assumed distribution shape. The weighted mean is not a promised finish date or a confidence interval.

Sources and method notes

Frequently asked questions

How do I use the PERT expected task duration calculator?

Complete the labeled inputs for PERT expected task duration. Use the units requested by each field, then read the displayed result alongside the method and limits below.

What is a worked example of PERT expected task duration?

For 3 optimistic days, 5 most-likely days, and 11 pessimistic days, (3 + 4×5 + 11) ÷ 6 = 34/6 ≈ 5.67 days.

What does the PERT expected task duration calculator calculate?

Calculate a PERT weighted duration estimate from optimistic, most-likely, and pessimistic task durations.

What assumptions apply to PERT expected task duration?

Three-point estimates depend on informed bounds and the assumed distribution shape. The weighted mean is not a promised finish date or a confidence interval.

Which method does the PERT expected task duration calculator use?

PERT expected duration = (optimistic + 4 × most likely + pessimistic) ÷ 6. Enter all three estimates for the same task and in the same unit.

Good calculators show their work.

CalcWorldHub is built around clear inputs and visible assumptions. Results are estimates for planning; check official sources or your provider’s terms when exact figures matter.

✓ Results update instantly
✓ No account required
✓ Privacy-friendly by design
✓ US and metric units