PERT task duration standard deviation calculator

Estimate the conventional PERT duration spread from the task range.

A better way to figure it out
Simple
inputs.
Clear result · useful details
Example · PERT standard deviation1.3333 days ↗

Calculator

4,000 tools
PERT task duration standard deviation calculator — Optimistic duration (days), Pessimistic duration (days) and calculation method
PERT task duration standard deviation calculator: inputs and calculation method.

How to use this calculator

Estimate PERT task-duration standard deviation from optimistic and pessimistic durations.

  1. Enter Optimistic duration (days), Pessimistic duration (days). Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.

Estimate PERT duration spread from optimistic and pessimistic bounds

The classical PERT approximation estimates duration standard deviation from the optimistic and pessimistic time bounds. The most-likely estimate contributes to expected duration, but not to this simple spread formula.

Inputs and units

Formula and method

PERT standard deviation σ = (pessimistic − optimistic) ÷ 6. The division by six follows the conventional approximation that the selected range spans roughly six standard deviations.

Worked example

For an optimistic duration of 3 days and a pessimistic duration of 11 days, σ = (11−3)/6 = 1.3333 days. A separate PERT expected-duration estimate uses the most-likely value.

Interpreting the result

The result is an estimated spread in days, not a deadline probability by itself. A probability calculation also needs an expected duration and assumptions about the duration distribution.

Assumptions and limits

The range and six-sigma convention are planning assumptions, not a statistical confidence interval. This page does not model dependencies, correlated risks, or empirical task-duration data.

Method references

Frequently asked questions

Why is most-likely duration not an input?

It affects the conventional PERT expected duration, but the standard-deviation approximation uses only the optimistic and pessimistic bounds.

How do I use the PERT task duration standard deviation calculator?

Enter Optimistic duration (days), Pessimistic duration (days). Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of PERT task duration standard deviation?

For an optimistic duration of 3 days and a pessimistic duration of 11 days, σ = (11−3)/6 = 1.3333 days. A separate PERT expected-duration estimate uses the most-likely value.

What does the PERT task duration standard deviation calculator calculate?

Estimate PERT task-duration standard deviation from optimistic and pessimistic durations.

What assumptions apply to PERT task duration standard deviation?

The range and six-sigma convention are planning assumptions, not a statistical confidence interval. This page does not model dependencies, correlated risks, or empirical task-duration data.

Good calculators show their work.

CalcWorldHub is built around clear inputs and visible assumptions. Results are estimates for planning; check official sources or your provider’s terms when exact figures matter.

✓ Results update instantly
✓ No account required
✓ Privacy-friendly by design
✓ US and metric units