How to use this calculator
Estimate discounted lifetime cost per unit of useful heat delivered.
- Enter Initial capital cost, Fixed operating and maintenance cost per year, Variable cost per MWh of useful heat, Useful heat delivered per year, MWh, then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Levelized cost of heat (LCOH) expresses project lifetime costs per discounted unit of useful heat. Entering constant annual heat and operating costs makes the calculation transparent while preserving the discounted-cash-flow structure used in energy-system comparisons.
Inputs and units
capitalCost— Initial capital cost- Currency units at time zero.
fixedOM— Fixed operating and maintenance cost per year- Currency units at each year-end.
variableCost— Variable cost per MWh of useful heat- Currency units per MWh delivered.
annualHeat— Useful heat delivered per year, MWh- Assumed constant over the project life.
lifetime— Project life, years- Enter 1 to 100 years.
discountRate— Discount rate, percent per year- Use the same price basis as the costs.
Formula
LCOH = [CAPEX + Σₜ₌₁ⁿ(O&Mₜ + variable costₜ × heatₜ)/(1+r)ᵗ] / [Σₜ₌₁ⁿ heatₜ/(1+r)ᵗ].
Method
For constant annual output and costs, calculate the present-value annuity factor over the project life. Add initial capital cost to the discounted fixed and variable operating costs, then divide by discounted heat output.
Worked example
With 100,000 initial capital cost, 5,000 fixed annual O&M, variable cost 10 per MWh, 1,000 MWh of useful heat per year, a 20-year life, and a 5% discount rate, LCOH is about 23.02 currency units per MWh.
Assumptions and limits
Assumes year-end annual operating costs and heat delivery, constant annual output and costs, and no taxes, replacements, subsidies, escalation, residual value, or decommissioning costs. Use a nominal rate with nominal amounts or a real rate with real amounts consistently.
Frequently asked questions
Why discount both costs and heat output?
It puts cash costs and delivered heat from different years on a common present-value basis.
Can I compare projects with different heat output?
Yes, if each estimate uses a consistent system boundary, useful-heat definition, price basis, and discount-rate convention.
Are fuel and electricity costs included?
Enter recurring energy-related operating costs in the variable cost per MWh field.
How do I use the Levelized Cost of Heat Calculator?
Enter Initial capital cost, Fixed operating and maintenance cost per year, Variable cost per MWh of useful heat, Useful heat delivered per year, MWh, then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Levelized Cost of Heat?
With 100,000 initial capital cost, 5,000 fixed annual O&M, variable cost 10 per MWh, 1,000 MWh of useful heat per year, a 20-year life, and a 5% discount rate, LCOH is about 23.02 currency units per MWh.
Reference: IEA SHC: Levelised Cost of Heat and the Calculations behind It. See our calculation methodology.