Levelized Cost of Storage (LCOS) Calculator

Estimate discounted storage cost per delivered megawatt-hour from capital cost, annual costs, energy throughput, and project life.

4,000 tools
Levelized Cost of Storage (LCOS) Calculator — Installed capital cost (currency units), Annual fixed operating cost (currency units/year), Annual charging electricity cost (currency units/year) and calculation method
Levelized Cost of Storage (LCOS) Calculator: inputs and calculation method.

How to use this calculator

Estimate discounted storage cost per delivered megawatt-hour from capital cost, annual costs, energy throughput, and project life.

  1. Enter Installed capital cost (currency units), Annual fixed operating cost (currency units/year), Annual charging electricity cost (currency units/year), Annual discharged energy (MWh/year), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Energy calculation

How this calculation works

LCOS compares a storage project’s life-cycle costs with the electricity it delivers. This simplified version discounts the initial investment and each year’s operating and charging costs, then divides by discounted discharged energy over the same analysis period.

Inputs and units

capex — Installed capital cost (currency units)
One-time installed cost at year 0.
om — Annual fixed operating cost (currency units/year)
Annual fixed maintenance and operating cost.
charging — Annual charging electricity cost (currency units/year)
Annual cost of electricity used to charge the storage system.
energy — Annual discharged energy (MWh/year)
Energy delivered from storage each year.
life — Analysis life (years)
Enter whole years; each year has the same assumed costs and output.
discount — Annual discount rate (%)
Nominal or real rate consistent with the costs and energy basis.

Formula

Displayed formula

PV cost = CAPEX + Σ[t=1..N] (fixed O&M + charging cost) ÷ (1 + r)^t. PV energy = Σ[t=1..N] discharged MWh ÷ (1 + r)^t. LCOS = PV cost ÷ PV energy.

Method

Use one currency for capital and annual costs, and enter discharged energy in MWh per year. Enter the analysis life and annual discount rate; the model places CAPEX at year 0 and recurring costs and energy at each year-end.

Worked example

With 1,000,000 installed cost, 100,000 annual operating and charging cost, 500 MWh delivered each year, a 10-year life, and an 8% discount rate, the present value of costs is about 1,671,008 and discounted energy is about 3,355.04 MWh. LCOS is about 498.06 per MWh.

Assumptions and limits

This estimate assumes flat annual throughput and costs, a constant discount rate, no residual value, no replacements, and no battery degradation. NREL’s SAM model includes more detailed lifetime and operating assumptions; this page is a transparent screening calculation, not a project finance model.

Frequently asked questions

Does LCOS include charging electricity?

This version includes the annual charging cost you enter; it does not derive that cost from a charging tariff or energy input.

Why discount discharged energy?

Discounting costs and energy on the same year-end schedule keeps the levelized ratio consistent with the selected discount rate.

Does this account for battery degradation?

No. It assumes the same delivered MWh every year; use a detailed storage model when throughput declines or replacements matter.

How do I use the Levelized Cost of Storage (LCOS) Calculator?

Enter Installed capital cost (currency units), Annual fixed operating cost (currency units/year), Annual charging electricity cost (currency units/year), Annual discharged energy (MWh/year), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Levelized Cost of Storage (LCOS)?

With 1,000,000 installed cost, 100,000 annual operating and charging cost, 500 MWh delivered each year, a 10-year life, and an 8% discount rate, the present value of costs is about 1,671,008 and discounted energy is about 3,355.04 MWh. LCOS is about 498.06 per MWh.