How to use this calculator
Calculate an activity driver rate and assign an overhead cost pool to a product or service.
- Enter Total activity cost pool ($), Total cost-driver units in the pool, Driver units consumed by this product or service. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Activity-based costing groups overhead into activity cost pools, divides each pool by its total cost-driver quantity, and assigns overhead according to the driver units consumed by a product or service.
Inputs and units
poolCost— Total activity cost pool ($)- Overhead cost assigned to this activity pool.
totalDriverUnits— Total cost-driver units in the pool- Total activity units for all products or services.
productDriverUnits— Driver units consumed by this product or service- The portion of total activity attributed to this product or service.
Formula
Activity rate = cost pool / total driver units; allocated overhead = activity rate × product driver units.
Method
Divide the entered activity pool cost by the total quantity of its cost driver. Multiply that rate by the driver quantity attributed to the selected product or service.
Worked example
A $40,000 setup cost pool divided by 2,000 machine setups gives $20 per setup. A product using 35 setups receives $700 of allocated overhead, or 1.75% of the pool.
Assumptions and limits
This is one activity-pool allocation. Use a separate rate for each materially different activity pool. The calculation allocates the entered pool cost; it does not decide which activities belong in a pool or choose a cost driver.
Frequently asked questions
How do I choose a cost driver?
Choose a measurable activity that reasonably explains how the cost pool is consumed.
Can the product use zero driver units?
Yes. Its allocation is zero while the activity rate remains based on total pool usage.
Does one rate cover all overhead?
Usually not. Activity-based costing uses separate rates for distinct activities and their cost drivers.
How do I use the Activity-Based Cost Allocation Calculator?
Enter Total activity cost pool ($), Total cost-driver units in the pool, Driver units consumed by this product or service. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Activity-Based Cost Allocation?
A $40,000 setup cost pool divided by 2,000 machine setups gives $20 per setup. A product using 35 setups receives $700 of allocated overhead, or 1.75% of the pool.
Reference: OpenStax activity-based cost pools, driver rates, and overhead allocation. See our calculation methodology.