Construction Change Order Value Rate Calculator

Compare net approved construction change-order value with the original awarded contract value.

4,000 tools
Construction Change Order Value Rate Calculator — Net approved change-order value, Original awarded contract value and calculation method
Construction Change Order Value Rate Calculator: inputs and calculation method.

How to use this calculator

Compare net approved construction change-order value with the original awarded contract value.

  1. Enter Net approved change-order value, Original awarded contract value. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Construction calculation

How this calculation works

This ratio shows cumulative approved contract-value changes relative to the original award. Include approved additions and credits as signed net value; exclude pending or rejected change orders.

Inputs and units

netApprovedChangeOrderValue — Net approved change-order value
Approved additions minus credits for the selected contract, in its currency.
originalAwardedContractValue — Original awarded contract value
Positive original contract award for the same scope and currency.

Formula

Displayed formula

Change-order value rate (%) = net approved change-order value ÷ original awarded contract value × 100.

Method

Add approved change orders and credits for one contract, then compare their net value with its original awarded amount. The revised value equals original value plus approved net change.

Worked example

A contract originally awarded at $2,500,000 has $125,000 in net approved change orders. The change-order value rate is 5.00%, and the revised value is $2,625,000.

Assumptions and limits

This ratio does not measure change-order count, schedule impact, or final cost performance. Use values from the same contract scope and currency.

Frequently asked questions

Are pending changes included?

No. Include only approved changes under the selected contract reporting rule.

How should credits be treated?

Subtract approved credits from approved additions to get the net signed change value.

Is this the project cost-overrun rate?

No. It compares approved scope changes with the original award, not final actual cost.

How do I use the Construction Change Order Value Rate Calculator?

Enter Net approved change-order value, Original awarded contract value. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Construction Change Order Value Rate?

A contract originally awarded at $2,500,000 has $125,000 in net approved change orders. The change-order value rate is 5.00%, and the revised value is $2,625,000.