How to use this calculator
Estimate concrete quantity for a constant rectangular continuous strip footing.
- Enter Total footing length (m), Footing width (m), Footing thickness (m), Ordering allowance (%). Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Continuous strip footing concrete volume explained
A strip footing is treated as a continuous rectangular prism along the entered centerline length; the order allowance is added after its geometric volume is calculated.
Inputs, symbols, and units
length— Total footing length (m)- Sum of centerline lengths; account for intersections consistently.
width— Footing width (m)- Horizontal width of the rectangular footing.
depth— Footing thickness (m)- Vertical concrete thickness.
waste— Ordering allowance (%)- Extra concrete allowance for handling and dimensional variation.
Formula and method
V_base = L × W × d; V_order = V_base × (1 + w/100).
Treat each section as a rectangular prism and sum lengths before entering. Apply the ordering allowance only after computing geometric volume.
A worked scenario
Total footing length (m) = 68; Footing width (m) = 0.55; Footing thickness (m) = 0.3; Ordering allowance (%) = 7.
- Geometric concrete volume: 11.22 m³
- Order volume with allowance: 12.0054 m³
- Equivalent litres: 11220 L
A 68 m strip footing at 0.55 m by 0.30 m has 11.22 m³ geometric volume, or about 12.01 m³ with 7% allowance.
Assumptions and edge cases
Constant dimensions are assumed. Steps, intersections, excavation overbreak, reinforcement displacement, and structural adequacy are excluded.
Reading the outputs
The main result is strip footing concrete volume; supporting outputs are labeled with their own units. Use the units shown beside each input and result.
Frequently asked questions
What does the continuous strip footing concrete volume calculate?
A 68 m strip footing at 0.55 m by 0.30 m has 11.22 m³ geometric volume, or about 12.01 m³ with 7% allowance.
Which inputs most affect strip footing concrete volume?
Treat each section as a rectangular prism and sum lengths before entering. Apply the ordering allowance only after computing geometric volume.
Can this result replace a site-specific or measured value?
Constant dimensions are assumed. Steps, intersections, excavation overbreak, reinforcement displacement, and structural adequacy are excluded.
How do I use the Continuous strip footing concrete volume calculator?
Enter Total footing length (m), Footing width (m), Footing thickness (m), Ordering allowance (%). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Continuous strip footing concrete volume?
Total footing length (m) = 68; Footing width (m) = 0.55; Footing thickness (m) = 0.3; Ordering allowance (%) = 7. Geometric concrete volume: 11.22 m³ Order volume with allowance: 12.0054 m³ Equivalent litres: 11220 L A 68 m strip footing at 0.55 m by 0.30 m has 11.22 m³ geometric volume, or about 12.01 m³ with 7% allowance.
Read our calculation methodology.