Earned value cost variance calculator
Compare earned value with actual cost to show whether completed work cost more or less than its earned budget. Enter the values below to calculate a clear estimate and see the method.
inputs.
How to use the Earned value cost variance calculator
Enter the budgeted value of completed work as EV and the actual cost of that same work as AC. Match the status date, reporting period, scope and currency before subtracting.
Inputs and units
Enter each value using the unit printed next to its field. Keep the period and accounting or project definitions consistent.
- Earned value (EV) is the budgeted cost of the work actually completed by the status date. It is not the amount invoiced or the total approved project budget.
- Actual cost (AC) is the cost incurred for that same completed work, using the same status date and currency as EV.
Formula and method
Cost variance = EV − AC.
Inputs follow the order shown above. The calculator keeps intermediate values unrounded and rounds only the displayed result.
Worked example
If completed work has an earned budget of $52,000 and its actual cost is $55,000, CV = $52,000 − $55,000 = −$3,000. The overrun is $3,000 for the work measured at that date; it is not necessarily the project’s final overrun.
Reading the result
CV = EV − AC. A negative value means the completed work cost more than its earned budget; a positive value means it cost less. This measures cost performance, not whether the project is ahead of schedule or its forecast final profit.
Assumptions and limitations
Use values from the same status date and scope baseline; a negative result indicates cost overrun in value terms.
Frequently asked questions
Is earned value the amount billed to the customer?
No. EV is the budgeted value of completed work. Billing and cash receipts can follow different schedules.
What does a negative cost variance mean?
Actual cost exceeds earned value for the same work and reporting date.
Can cost variance tell me whether work is late?
No. Schedule variance compares earned value with planned value, whereas this tool compares earned value with actual cost.
Can I mix a monthly EV figure with cumulative AC?
No. Match the period, status date, work scope and currency before subtracting.