Earned value cost variance calculator

Compare earned value with actual cost to show whether completed work cost more or less than its earned budget. Enter the values below to calculate a clear estimate and see the method.

A better way to figure it out
Clear
inputs.
∑
Clear result · useful details
Free calculatorNo signup ✓

Related calculators

These pages answer closely related questions.

Browse project management tools →

Earned value cost variance calculator — Earned value (EV), Actual cost (AC) and calculation method
Earned value cost variance calculator: inputs and calculation method.
Free calculator guide

How to use the Earned value cost variance calculator

Enter the budgeted value of completed work as EV and the actual cost of that same work as AC. Match the status date, reporting period, scope and currency before subtracting.

Inputs and units

Enter each value using the unit printed next to its field. Keep the period and accounting or project definitions consistent.

Formula and method

Cost variance = EV − AC.

Inputs follow the order shown above. The calculator keeps intermediate values unrounded and rounds only the displayed result.

Worked example

If completed work has an earned budget of $52,000 and its actual cost is $55,000, CV = $52,000 − $55,000 = −$3,000. The overrun is $3,000 for the work measured at that date; it is not necessarily the project’s final overrun.

Reading the result

CV = EV − AC. A negative value means the completed work cost more than its earned budget; a positive value means it cost less. This measures cost performance, not whether the project is ahead of schedule or its forecast final profit.

Assumptions and limitations

Use values from the same status date and scope baseline; a negative result indicates cost overrun in value terms.

Frequently asked questions

Is earned value the amount billed to the customer?

No. EV is the budgeted value of completed work. Billing and cash receipts can follow different schedules.

What does a negative cost variance mean?

Actual cost exceeds earned value for the same work and reporting date.

Can cost variance tell me whether work is late?

No. Schedule variance compares earned value with planned value, whereas this tool compares earned value with actual cost.

Can I mix a monthly EV figure with cumulative AC?

No. Match the period, status date, work scope and currency before subtracting.