Estimate at completion calculator
Project total cost at completion using budget at completion and current cost performance. Enter the values below to calculate a clear estimate and see the method.
inputs.
Related calculators
How to use the Estimate at completion calculator
Project total cost at completion using budget at completion and current cost performance. Use it when you need this specific estimate and want to inspect the inputs behind the result.
Inputs and units
Use BAC and CPI from the same project baseline and reporting cut-off.
- Budget at completion (BAC): use the value defined for your scenario.
- Earned value (EV): use the value defined for your scenario.
- Actual cost (AC): use the value defined for your scenario.
Formula and method
EAC = BAC ÷ CPI, where CPI = EV ÷ AC.
This CPI-based estimate projects final cost as BAC/CPI, assuming current cost efficiency continues.
Worked example
With BAC $120,000, EV $52,000, and AC $55,000, EAC is about $126,923.08.
Reading the result
The estimate projects final cost as BAC divided by the entered CPI. Compare it with BAC; it assumes current cost efficiency continues and does not predict a completion date.
Assumptions and limitations
This method assumes current cost efficiency continues; other EAC methods may fit different project conditions.
Source and method
GAO discusses credible cost estimates and earned-value management; this calculator is a single CPI-based forecast, not a full cost estimate. U.S. Government Accountability Office — Cost Estimating and Assessment Guide.
Frequently asked questions
How do I calculate estimate at completion?
EAC = BAC ÷ CPI, where CPI = EV ÷ AC. The worked example shows how the inputs map to the result.
Which performance index drives this estimate?
It uses CPI=EV/AC from the entered values and assumes the current cost efficiency continues. Keep EV and AC for the same status date and budget basis.
When is BAC divided by CPI a useful EAC forecast?
It is a simple forecast when current cumulative cost efficiency is a reasonable guide to remaining work. If future work or remaining-cost conditions changed, another EAC method may be more suitable.
How do I use the Estimate at completion calculator?
Enter Budget at completion (BAC), Earned value (EV), Actual cost (AC). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Estimate at completion?
With BAC $120,000, EV $52,000, and AC $55,000, EAC is about $126,923.08.