Generator size calculator

Estimate generator running and startup watt requirements from simultaneous loads and one motor surge.

4,000 tools
Generator size calculator — Other simultaneous running loads (W), Largest motor running input (W), Motor startup multiplier and calculation method
Generator size calculator: inputs and calculation method.

How to use this calculator

Estimate generator running and startup watt requirements from simultaneous loads and one motor surge.

  1. Enter Other simultaneous running loads (W), Largest motor running input (W), Motor startup multiplier, Capacity reserve (%). Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Energy calculation

How this calculation works

Generator selection should consider loads that operate together and the short surge when a large motor starts. This estimate sums other running loads, applies a startup multiplier to one motor, and adds a reserve margin.

Inputs and units

other — Other simultaneous running loads (W)
Combined non-motor load expected during startup.
motor — Largest motor running input (W)
Electrical running input of the motor with the highest starting surge.
surge — Motor startup multiplier
Starting watts divided by running input watts.
reserve — Capacity reserve (%)
Additional margin above the estimated peak.

Formula

Displayed formula

Peak = other running watts + motor running watts × startup multiplier. Generator target = peak × (1 + reserve percentage/100).

Method

Enter the simultaneous non-motor load, largest motor input, its startup multiplier, and a reserve. It assumes one motor starts while all listed loads remain on.

Worked example

With 1,500 W of other loads, a 1,200 W motor, a 3× startup multiplier, and 25% reserve, startup peak is 5,100 W and the estimated generator target is 6,375 W.

Assumptions and limits

Starting current varies by motor, voltage, power factor, and generator response. Check nameplates and continuous/surge ratings and follow electrical codes; this estimate is not installation advice.

Frequently asked questions

Does reserve replace motor surge?

No. The motor surge is applied first, and the reserve is added afterward.

Which motor value should I use?

Use the motor with the largest documented starting demand among the loads that may start.

Can horsepower alone size a generator?

This calculation uses electrical input watts. Verify both starting and continuous ratings on equipment labels.

How do I use the Generator size calculator?

Enter Other simultaneous running loads (W), Largest motor running input (W), Motor startup multiplier, Capacity reserve (%). Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Generator size?

With 1,500 W of other loads, a 1,200 W motor, a 3× startup multiplier, and 25% reserve, startup peak is 5,100 W and the estimated generator target is 6,375 W.