How to use this calculator
Rank jobs by increasing critical ratio to highlight work with the least relative time before its deadline.
- Enter Days until each job due date, Remaining processing days. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Job critical ratio priority ranking explained
How the calculation works
Due-date slack horizon divided by remaining processing time
Static priority rule; no resource constraints or sequence-dependent setups are optimized..
Set up the calculation
d— Days until each job due date- Remaining calendar or workdays until each job is due, entered as a comma-separated list.
t— Remaining processing days- Remaining processing days for the corresponding jobs, in the same list order. The ratio is due time divided by processing time; smaller values signal less schedule slack.
Limits of this model
Static priority rule; no resource constraints or sequence-dependent setups are optimized.
Check this example
Days until each job due date = 20, 10; Remaining processing days = 5, 6.
- Priority job order: 2, 1
- Ratios in original order: 4, 1.666667
Reading the outputs
A critical ratio below 1 means remaining work time exceeds time until due and signals a late-job risk; 1 means the schedule is exactly tight, and values above 1 indicate more time than the remaining processing requirement. Lower ratios are ranked first.
Frequently asked questions
Does a ratio below one indicate pressure?
Remaining processing time exceeds the time to due date in this model.
Can due dates be negative?
Yes, that represents overdue jobs.
Does the rule find the globally best schedule?
No.
How do I use the Job critical ratio priority ranking calculator?
Enter Days until each job due date, Remaining processing days. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Job critical ratio priority ranking?
Days until each job due date = 20, 10; Remaining processing days = 5, 6. Priority job order: 2, 1 Ratios in original order: 4, 1.666667
Read our calculation methodology.