How to use this calculator
Sequence jobs that all visit machine one then machine two to minimize ideal two-machine makespan.
- Enter Processing times on machine one, Processing times on machine two. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Johnson two machine flow shop schedule explained
A numerical walkthrough
Processing times on machine one = 3, 8, 4; Processing times on machine two = 5, 2, 6.
- Johnson job order: 1, 3, 2
- Makespan: 17 time units
The model behind the numbers
Johnson earliest-first-machine / latest-second-machine rule
Assumptions: every job is available initially, jobs are not interrupted, setup time does not depend on job order, and all jobs follow the same two-machine route.
MIT's scheduling notes develop Johnson's rule for a two-machine flow shop and discuss its optimality. MIT scheduling notes.
What to enter
a— Processing times on machine one- Processing time for each job on machine 1. List jobs in their shared job-number order.
b— Processing times on machine two- Processing time for the same jobs on machine 2, in exactly the same order as machine 1.
Interpreting the result
The reported sequence is optimal for this two-machine model under those assumptions; makespan is the elapsed time until both machines finish the schedule.
Frequently asked questions
Can a job skip a machine?
Not in this model.
How are ties handled?
Original job order breaks equal minimum-time ties.
Does it optimize three machines generally?
No.
How do I use the Johnson two machine flow shop schedule calculator?
Enter Processing times on machine one, Processing times on machine two. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Johnson two machine flow shop schedule?
Processing times on machine one = 3, 8, 4; Processing times on machine two = 5, 2, 6. Johnson job order: 1, 3, 2 Makespan: 17 time units
Read our calculation methodology.