How to use this calculator
Summarize purchase-order-to-receipt lead times in calendar days across completed supplier orders.
- Enter Supplier lead times (calendar days). Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Enter elapsed calendar days from purchase-order release to receipt for each completed order. The calculator reports sample count, mean, median, minimum, and maximum. Apply the same receipt event and partial-delivery rule to every observation.
Inputs and units
leadTimesDays— Supplier lead times (calendar days)- Enter one purchase-order-to-receipt duration per completed order.
Formula
Mean supplier lead time = sum of order-to-receipt days ÷ completed orders; median and range use the sorted observations.
Method
Sort the nonnegative day values, then calculate the arithmetic mean, median, minimum, and maximum.
Worked example
For 6, 10, 14, and 20 days, mean lead time is 12.50 days, median is 12.00 days, and range is 6–20 days.
Assumptions and limits
This summarizes completed orders and is not a future delivery promise. Define whether lead time ends at first or complete receipt and treat partial deliveries consistently.
Frequently asked questions
When does lead time start and end?
Use purchase-order release as start and the chosen receipt event as end for every order.
How should partial deliveries be handled?
Choose first receipt or complete receipt as the end event and apply it consistently.
Why report the median?
It is less sensitive to a small number of unusually long supplier orders.
How do I use the Supplier Lead-Time Distribution Calculator?
Enter Supplier lead times (calendar days). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Supplier Lead-Time Distribution?
For 6, 10, 14, and 20 days, mean lead time is 12.50 days, median is 12.00 days, and range is 6–20 days.