How to use this calculator
Compare the marginal direct cost per day saved for one crashable project activity.
- Enter Normal duration (days), Crash duration (days), Normal direct cost, Crash direct cost. Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Activity crashing cost slope explained
Use Normal duration (days) with Crash duration (days) to reproduce the sample calculation, then review the stated limits before carrying the result into another scenario.
A numerical walkthrough
Normal duration (days) = 10; Crash duration (days) = 6; Normal direct cost = 1000; Crash direct cost = 1800.
- Direct crash-cost slope: 200 currency/day
A slope of 200 currency units per day is the direct-cost increase for each day saved between these activity endpoints. It describes this activity's linear time-cost segment; it does not establish that the activity is critical or that the whole project will finish sooner.
The model behind the numbers
(cc-cn)/(tn-tc)
Symbols use the input definitions below. Linear time-cost interpolation between the two entered endpoints; activity criticality and whole-project optimization are excluded..
What to enter
tn— Normal duration (days)- Normal duration (days).
tc— Crash duration (days)- Crash duration (days).
cn— Normal direct cost- Normal direct cost.
cc— Crash direct cost- Crash direct cost.
Interpreting the result
Linear time-cost interpolation between the two entered endpoints; activity criticality and whole-project optimization are excluded.
Frequently asked questions
Will crashing this activity shorten the project?
Only if the network and other paths allow it.
Can duration stay equal?
No, the endpoints must offer a positive reduction.
Does it include indirect daily costs?
No, compare them separately.
How do I use the Activity crashing cost slope calculator?
Enter Normal duration (days), Crash duration (days), Normal direct cost, Crash direct cost. Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Activity crashing cost slope?
Normal duration (days) = 10; Crash duration (days) = 6; Normal direct cost = 1000; Crash direct cost = 1800. Direct crash-cost slope: 200 currency/day A slope of 200 currency units per day is the direct-cost increase for each day saved between these activity endpoints. It describes this activity's linear time-cost segment; it does not establish that the activity is critical or that the whole project will finish sooner.
Read our calculation methodology.