How to use this calculator
Estimate expected monetary exposure from a list of risk probabilities and their cost impacts.
- Enter Risk probabilities (%, comma separated), Cost impacts (currency, comma separated). Match the units shown beside each field and review the result together with the assumptions below.
- Read the worked example below to check the expected input format and result.
- Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
How this calculation works
Expected monetary value weights each risk’s cost by its assessed probability. Summing the weighted exposures creates a planning estimate, but not a guarantee or a complete contingency reserve.
Inputs and units
prob— Risk probabilities (%, comma separated)- One probability percentage per risk scenario.
impact— Cost impacts (currency, comma separated)- Matching cost consequence for each listed risk.
Formula
EMV = Σ(probabilityᵢ × cost impactᵢ).
Worked example
Three risks at 20% × 5,000, 10% × 12,000, and 5% × 30,000 produce EMV 1,000 + 1,200 + 1,500 = 3,700.
Assumptions and limits
Assumes entered probabilities and impacts are meaningful and costs are comparable. Use additive cost impacts without double-counting the same consequence. The sum does not estimate joint outcomes, timing, upside opportunities, or risk-aversion preferences.
Frequently asked questions
Is EMV a worst-case budget?
No. It is a probability-weighted expected value and may be much lower than a severe scenario.
Can risks be dependent?
Linearity of expectation permits adding expected additive costs even when risks are dependent. Dependence affects joint outcomes, variability and tail loss, which this calculator does not estimate.
Can opportunities be included?
This page is for nonnegative cost impacts; analyze opportunities separately or use a method that handles upside outcomes.
How do I use the Expected monetary value project risk calculator?
Enter Risk probabilities (%, comma separated), Cost impacts (currency, comma separated). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Expected monetary value project risk?
Three risks at 20% × 5,000, 10% × 12,000, and 5% × 30,000 produce EMV 1,000 + 1,200 + 1,500 = 3,700.