Schedule performance index calculator
Compare earned value with planned value as a schedule-performance ratio at a status date. Enter the values below to calculate a clear estimate and see the method.
inputs.
Related calculators
Earned-value variance and cost indexes complement SPI but use distinct outputs and interpretations.
How to use the Schedule performance index calculator
Compare earned value with planned value as a schedule-performance ratio at a status date. Compare EV and PV for the same work scope at one status date; SPI is a schedule-performance ratio, not calendar time.
Inputs and units
Enter EV and PV for the same work scope and status date, in matching value units; PV is the denominator.
- Earned value (EV): Budgeted value of work completed by the status date.
- Planned value (PV): Budgeted value of work scheduled by that same status date.
Formula and method
SPI = EV ÷ PV.
EV and PV must share the same status date and value basis; SPI is a ratio, not calendar time.
Worked example
$52,000 EV divided by $50,000 PV gives SPI = 1.04.
Reading the result
SPI=1 means earned value equals planned value at the status date; above 1 is more earned value than planned, not a number of days.
Assumptions and limitations
SPI above 1 means earned value exceeds planned value; the ratio does not directly convert to days early or late.
Frequently asked questions
What does SPI compare?
SPI=EV/PV compares earned value with planned value at one status date. Use matching scope, currency or budget units, and measurement rules.
Does SPI tell how many days early or late a project is?
No. It is a value-based index. SPI above 1 means earned value exceeds planned value; calendar-time variance needs schedule data.
Why must planned value be positive?
PV is the denominator. If PV is zero, SPI is undefined and should not be interpreted as a numerical performance index.
How do I use the Schedule performance index calculator?
Enter Earned value (EV), Planned value (PV). Match the units shown beside each field and review the result together with the assumptions below.
What is a worked example of Schedule performance index?
$52,000 EV divided by $50,000 PV gives SPI = 1.04.