To-complete performance index calculator

Find the cost efficiency required on remaining work to meet the original budget. Enter the values below to calculate a clear estimate and see the method.

A better way to figure it out
Clear
inputs.
∑
Clear result · useful details
Free calculatorNo signup ✓

Related calculators

SPI, CPI, and cost variance provide related earned-value indicators; an EAC estimate addresses a forecast rather than required efficiency.

Browse project management tools →

To-complete performance index calculator — Budget at completion (BAC), Earned value (EV), Actual cost (AC) and calculation method
To-complete performance index calculator: inputs and calculation method.
Free calculator guide

How to use the To-complete performance index calculator

Find the cost efficiency required on remaining work to meet the original budget. This BAC form expresses the cost efficiency the remaining work would need to meet the original budget.

Inputs and units

Enter BAC, EV, and AC in matching value units for the same project status date; BAC−AC must be nonzero.

Formula and method

TCPI = (BAC − EV) ÷ (BAC − AC).

EV, AC, and BAC must use the same status date and value basis; BAC=AC makes this form undefined.

Worked example

For BAC $120,000, EV $52,000, and AC $55,000, TCPI ≈ 1.0462.

Reading the result

TCPI is the cost efficiency required on remaining work to meet BAC; compare it with past performance before treating that target as feasible.

Assumptions and limitations

The original-budget form requires BAC > AC; compare the required index with demonstrated performance before planning.

Frequently asked questions

What does TCPI measure?

TCPI=(BAC−EV)/(BAC−AC) estimates the cost efficiency required on remaining work to meet the original budget, using matching status-date values.

What does a TCPI above 1 mean?

It requires future work to earn more value per cost unit than one-to-one efficiency. Compare it with demonstrated performance before treating the goal as feasible.

What if actual cost equals the budget at completion?

The denominator BAC−AC is zero, so this original-budget form is undefined; it cannot produce a finite required-efficiency ratio.

How do I use the To-complete performance index calculator?

Enter Budget at completion (BAC), Earned value (EV), Actual cost (AC). Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of To-complete performance index?

For BAC $120,000, EV $52,000, and AC $55,000, TCPI ≈ 1.0462.