CalcWorldHub
Free online calculator · no signup

Sprint team capacity calculator

Estimate net team working hours for a sprint after planned time off and a user-selected focus factor.

4,000 tools
Sprint team capacity calculator — Available team members, Sprint workdays, Work hours per person-day and calculation method
Sprint team capacity calculator: inputs and calculation method.

How to use this calculator

Estimate net team working hours for a sprint after planned time off and a user-selected focus factor.

  1. Enter Available team members, Sprint workdays, Work hours per person-day, Planned time off (person-days), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.
  2. Read the worked example below to check the expected input format and result.
  3. Compare another scenario by changing one input at a time. Use Reset to return to the starting values.
Project management calculation

How this calculation works

Sprint capacity starts with each team member’s available workdays and hours, then accounts for planned absences and time that cannot be spent on sprint work. This calculator keeps capacity in hours or person-days; it does not infer story points from availability.

Inputs and units

teamSize — Available team members
People included in the sprint capacity estimate.
sprintWorkdays — Sprint workdays
Working days in the sprint, excluding non-working days according to your team calendar.
hoursPerDay — Work hours per person-day
Scheduled working hours per person per sprint workday.
timeOffPersonDays — Planned time off (person-days)
Sum of leave or other unavailable days across all team members.
focusPercent — Focus factor (%)
User-selected share of scheduled time expected to remain for sprint work after routine overhead.

Formula

Displayed formula

Available person-days = team size × sprint workdays − time-off person-days. Scheduled hours = available person-days × work hours per day. Focus-adjusted capacity = scheduled hours × focus factor ÷ 100.

Method

Enter the number of people, working days, work hours per person-day, total person-days away, and a focus factor. A focus factor of 80% means the plan treats 80% of scheduled hours as available for sprint work after meetings and other interruptions.

Worked example

A six-person team with 10 workdays has 60 person-days. Subtracting 3 person-days of leave leaves 57; at 8 hours per day and an 80% focus factor, capacity is 57 × 8 × 0.80 = 364.8 hours.

Assumptions and limits

This is a planning estimate, not a commitment or velocity forecast. Focus factor is a team assumption and can vary by work type, holidays, meetings, support duties, and staffing. Do not interpret hours as story points without a separately observed team relationship.

Frequently asked questions

What does the focus factor represent?

It is a planning assumption for the share of scheduled hours available to sprint work after recurring meetings, support, and interruptions.

Should time off be entered per person or as a team total?

Enter the sum in person-days; for example, two people away for one day each equals 2 person-days.

Can this calculator predict story points?

No. Story points depend on a team’s own estimation and historical delivery; the result here is available work time only.

How do I use the Sprint team capacity calculator?

Enter Available team members, Sprint workdays, Work hours per person-day, Planned time off (person-days), then complete the remaining labeled fields. Match the units shown beside each field and review the result together with the assumptions below.

What is a worked example of Sprint team capacity?

A six-person team with 10 workdays has 60 person-days. Subtracting 3 person-days of leave leaves 57; at 8 hours per day and an 80% focus factor, capacity is 57 × 8 × 0.80 = 364.8 hours.